Siemens to add battery storage as part of gas power plant overhaul

By John Parnell
May 30, 2019
LinkedIn
Twitter
Reddit
Facebook
Email
The SGT-800 industrial gas turbine installed at the BASF site. Source: Siemens.

Siemens will install a battery storage system as part of the overhaul of a gas power plant for chemicals giant BASF.

As well as replacing the gas turbines at the industrial power plant in Schwarzheide, Germany, a SIESTART battery system has been installed to provide blackstart capabilities. Siemens will also provide a 15-year service contract.

“Adapting the new gas turbine to the existing plant and carrying out the other necessary renovations require complex individual planning and extensive engineering expertise,” said Thorbjörn Fors, CEO of the Service Distributed Generation and Oil & Gas within Siemens Gas and Power. “Siemens is one of the few suppliers on the market with all the manufacturing and engineering skills needed to reliably implement such a demanding project.”

The battery system will be provided by Fluence, the joint venture between AES and Siemens. The company said BASF will benefit from blackstart capabilities, islanding, if required, and a more reliable power supply.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The site at Schwarzheide currently has two gas turbines for power and two Siemens steam turbines providing steam for BASF manufacturing and processing activities. BASF has ordered one efficient 57MW gas turbine, which Siemens says will reduce both costs and carbon.

“We are pleased to work with Siemens for the modernization of our combined cycle power plant. We continue our long-term partnership with this project,” said Jürgen Fuchs, Chairman of the Management Board of BASF Schwarzheide GmbH.

Read Next

Premium
November 26, 2025
The US market is expected to be the largest source of revenue and driver of activity for Fluence in 2026, and a second battery cell deal with a domestic supplier is imminent.
November 26, 2025
Potentia Energy has received federal environmental approval for its 1,000MWh Tallawang Solar Hybrid project, and Fluence has delivered its Gridstack battery energy storage equipment to Ampyr Australia’s 600MWh Bulabul Battery installation.
Sponsored
November 26, 2025
As Australia accelerates its transition toward renewables, demand for reliable & sustainable energy storage solutions has never been higher.  
November 25, 2025
OptiGrid, an Australian battery optimisation and trading intelligence platform, has partnered with Acacia Energy to accelerate the deployment of battery storage for commercial and industrial (C&I) customers.
November 25, 2025
A week of claimed first-of-their-kind advances in Germany’s BESS market, including the combination of monitoring, diagnostics and energy trading on one platform, an optimisation deal allowing multiple companies to trade one asset, and a law change accelerating permitting.