Siemens to add battery storage as part of gas power plant overhaul

By John Parnell
May 30, 2019
LinkedIn
Twitter
Reddit
Facebook
Email
The SGT-800 industrial gas turbine installed at the BASF site. Source: Siemens.

Siemens will install a battery storage system as part of the overhaul of a gas power plant for chemicals giant BASF.

As well as replacing the gas turbines at the industrial power plant in Schwarzheide, Germany, a SIESTART battery system has been installed to provide blackstart capabilities. Siemens will also provide a 15-year service contract.

“Adapting the new gas turbine to the existing plant and carrying out the other necessary renovations require complex individual planning and extensive engineering expertise,” said Thorbjörn Fors, CEO of the Service Distributed Generation and Oil & Gas within Siemens Gas and Power. “Siemens is one of the few suppliers on the market with all the manufacturing and engineering skills needed to reliably implement such a demanding project.”

The battery system will be provided by Fluence, the joint venture between AES and Siemens. The company said BASF will benefit from blackstart capabilities, islanding, if required, and a more reliable power supply.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The site at Schwarzheide currently has two gas turbines for power and two Siemens steam turbines providing steam for BASF manufacturing and processing activities. BASF has ordered one efficient 57MW gas turbine, which Siemens says will reduce both costs and carbon.

“We are pleased to work with Siemens for the modernization of our combined cycle power plant. We continue our long-term partnership with this project,” said Jürgen Fuchs, Chairman of the Management Board of BASF Schwarzheide GmbH.

15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

January 29, 2026
Power firm RWE is about to start building a 400MW/800MWh BESS project in Germany, among the largest in the country to reach the construction stage. In related news, Kyon Energy has connected a 282MWh project to the grid, possibly the largest in the country to reach that milestone.
Premium
January 28, 2026
Leading BESS owner-operators across Europe discuss the key trends around the financing and deployment of grid-scale projects, with the segment now the driver of continent-wide deployments according to trade body SolarPower Europe.
January 28, 2026
US sodium-ion (Na-ion) battery technology company Unigrid has begun international shipments of its proprietary sodium cobalt oxide (NCO) cathode cells at commercial volume.
January 28, 2026
Bigger, longer-duration projects and more sophisticated deal structuring are driving the energy storage industry forward, but a lack of common approaches from transmission system operators (TSOs) remains a challenge.
January 27, 2026
More BESS news from across Europe, with ContourGlobal and Alpiq striking sizeable deals in Greece and France, Iberdrola putting projects into operation in Spain, and other project news in Germany, Poland, Denmark and Southeast Europe.