Scottish C&I project gets ‘no-money-down’ 2MW Tesla battery

LinkedIn
Twitter
Reddit
Facebook
Email
Image: Ardagh Glass via Twitter.

A glass packaging facility in Scotland is getting a 2MW Tesla battery on a ‘no-money-down’ deal after Irish state-owned utility ESB agreed to take on the risk for raising commercial revenues from the asset.

The project for Ardagh Glass’ packaging plant in Irvine, west Scotland, was completed a couple of weeks ago by Ardagh and ESB (Electricity Supply Board), headquartered in neighbouring Ireland. The battery system is aimed at helping Ardagh manage its onsite electricity costs.

It will store power during periods of low demand from the grid for use at peak times while backing up the facility’s must-run functions. ESB also said it would also use the battery for delivering frequency response services to the grid via a separate operating platform, supplied by GridBeyond, an aggregator formerly trading under the brand name Endeco.

ESB corporate press officer Susan O’Connor told Energy-Storage.News that the project will be installed on an outdoor plinth at the Irvine facility, utilising existing electrical switchgear onsite. ESB’s Smart Energy Services division will be responsible for the peak demand management and backup functions of the system while GridBeyond will coordinate and execute market participation for grid services.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

O’Connor also explained how ESB was able to “own the battery and deliver it to Ardagh with no investment from their side.”

“As a utility operating in all sectors of the market, we are able to invest in energy assets for their lifetime, and that allows us to manage one of the big challenges here: the revenues, for a significant investment, are only certain over a period of one or two years, versus 10+ years of the asset lifetime,” O’Connor said, adding that Tesla’s 10-year warranty added some investment security to the deal.

ESB’s O’Connor said the battery is intended to enter British transmission network operator (TNO) National Grid’s market for Dynamic Firm Frequency Response (DFFR), defined by National Grid as “a continuously provided service used to manage the normal second-by-second changes on the system”. It requires fast-responding assets, able to match imbalances in network supply and demand, with lithium batteries considered a good fit.

ESB said it is targeting businesses that spend more than €1 million (US$1.21 million) a year on energy with such schemes, working to reduce both costs and emissions.

13 October 2026
London, UK
Now in its second edition, the Summit provides a dedicated platform for UK & Ireland’s BESS community to share practical insights on performance, degradation, safety, market design and optimisation strategies. As storage deployment accelerates towards 2030 targets, attendees gain the tools needed to enhance returns and operate resilient, efficient assets.

Read Next

Premium
September 17, 2026
Energy-Storage.news Premium speaks with Randolph Mann, CEO at developer esVolta at the 2026 US Battery Asset Management Summit in Garden Grove, California.
Premium
September 16, 2026
Energy-Storage.news Premium speaks with David Miller, CCO of optimiser Gridmatic, at the 2026 US Battery Asset Management Summit in Garden Grove, California.
September 16, 2026
Recent moves from the US federal government could prove more damaging to US renewable energy deployment than foreign entity of concern (FEOC) compliance requirements, according to legal and industry experts.
Premium
September 16, 2026
On 26 August, US President Donald Trump banned the import of inverters, transformers and other power equipment citing a potential risk to US grid security, via emergency executive order (EO).
September 15, 2026
Massachusetts Governor Maura Healey has released a comprehensive framework establishing principles and expectations for responsible data centre development in the state.