Funding boost for Australia’s first compressed air energy storage system

February 12, 2019
LinkedIn
Twitter
Reddit
Facebook
Email
How the Angas CAES project will look above ground. Source: Hydrostor.

The Australian Renewable Energy Agency (ARENA) has approved A$6 million of funding for the country’s first compress air energy storage (CAES) project.

US-firm Hydrostor will convert a disused zinc mine in South Australia into a below-ground air-storage cavern. The 5MW /10MWh demonstration plant will provide load shifting, frequency regulation and grid security. The Angas mine is currently a brownfield site in a state of “care and maintenance”. The company had been looking for a site in Australia since summer 2017.

The latest funds add to A$3 million it has received from the South Australian Government’s Renewable Energy Technology Fund.

“While being a commercial demonstration at this stage, Hydrostor’s innovative way to store energy with air could add to Australia’s grid-scale storage capability, complementing pumped hydro and batteries,” said Darren Miller, CEO, ARENA.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“Compressed air storage has the potential to provide similar benefits to pumped hydro energy storage, however it has the added benefits of being flexible with location and topography, such as utilising a cavern already created at a disused mine site,” added Miller.

South Australia has become a hotbed for emerging energy storage technologies. A major blackout event in the territory in 2016 exposed the grid’s unsuitability for a modern power generation mix. Since then, the Tesla “100 days” battery install, lithium battery trials and the world’s largest virtual power plant have all been deployed.

Read Next

May 8, 2026
Australian utility AGL has said adding its Liddell and Tomago BESS to its existing coal-fired generation could boost portfolio returns by 10%
May 7, 2026
Australia has installed 380,712 home battery storage systems, representing 10.7GWh of storage capacity, since the introduction of the Cheaper Home Batteries Program last year, Chris Bowen, Australia’s minister for climate change and energy, has disclosed.
May 6, 2026
Queensland has become the first state in Australia’s National Electricity Market (NEM) to discharge over 100GWh from utility-scale battery storage systems in a single month.
May 6, 2026
Fortescue’s AI-enabled batteries stabilised its Pilbara mining grid without spinning generators, reversing electron flow in nanoseconds during disruption.
May 5, 2026
New South Wales BESS set two charging records on 2 May, reaching 1,240MW of charging power and capturing 11.9% of state consumption.