EnergyAustralia ponders world’s largest seawater pumped hydro energy storage plant

LinkedIn
Twitter
Reddit
Facebook
Email

The proposed project would be situated at the northern end of the Spencer Gulf with 300 metres elevation. Credit: EnergyAustralia
Major power firm EnergyAustralia is studying the feasibility of building a huge pumped hydroelectric energy storage project in the Spencer Gulf of South Australia.

Standing at 100MW with six-to-eight hours of storage, this would not only be the second ever seawater-based pumped hydro storage project in the world, it would also be the largest.

EnergyAustralia claimed that the project would account for the equivalent of 60,000 home battery storage systems, but at a third of the price, while helping to stabilise and integrate clean energy to the grid.

Air-conditioning is clearly a major challenge for the country’s grid operators and the project could offer some respite.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

“On hot days, when demand spikes, a pumped hydro plant can be brought into action in minutes, keeping the lights on and costs down,” said EnergyAustralia managing director Catherine Tanna. “We’re really excited by its potential.”

The proposed project would be situated at the northern end of the Spencer Gulf with 300 metres elevation, two kilometres from the coastline and in close proximity to high voltage transmission lines.

Pumped hydro storage involves pumping water from a lower reservoir to a higher reservoir, when energy produced is cheaper or in excess. In peak periods, the water can be released downwards to run a turbine, which then generates electricity.

Since 2013, EnergyAustralia’s project partners, Melbourne Energy Institute and engineering consultancy Arup Group, have been investigating how to adapt traditional fresh water pumped hydro for use with seawater instead – a need for innovation driven by Australia’s dry conditions.

The feasibility study for the new project is touted for completion by mid-2017 and if then approved via consultation with stakeholders and government, it will require a two-year construction period.

Prime minister Malcolm Turnbull has also written to the Australian Renewable Energy Agency (ARENA) and the Clean Energy Finance Corporation (CEFC) asking them to prioritise pumped hydro and storage. Grid stabilising has become a major poltical issue in Australia over the last few months after several disruptive blackouts in South Australia and other states. This led to a furore surrounding integration of renewables into the grid with various energy bodies and environmentalists arguing over whether renewbales had any role in the power cuts.

Tellingly, even Turnbull noted that a storm had caused the South Australia power issues.

Construction starts on solar-plus-hydro storage project

In related news, construction has started on the first phase of what will be Australia’s largest solar plant, just off the back of reaching financial closure.

While a second phase of 270MW of solar is planned at the 50MW Kidston solar farm at a gold mine in Queensland, energy firm Genex Power is also considering developing an accompanying 250MW Kidston pumped storage hydro project, which it found could be connected to the solar plant in a recent study.

This would be the first Australian example of co-locating a large-scale solar farm with a large-scale pumped hydro storage project.

Genex forecasts that the pumped hydro storage project will support 1,500MWh of continuous power in a single 6-hour generation cycle. Despite many instances of pumped storage deployment worldwide, there are only three pumped hydro storage projects operating in Australia at Tumut and the Shoalhaven in New South Wales and at Wivenhoe in Queensland.

The Kidston solar project received a debt funding arrangement of approximately AU$100 million (US$76.9 million) from Société Générale, with the Clean Energy Finance Corporation (CEFC) taking care of the EPC requirements and O&M costs.

The Kidston Gold mine. Credit: Genex

Read Next

September 18, 2025
Tesla has issued a product recall on its Powerwall 2 residential battery storage solution across Australia due to a “battery cell defect” from a third-party supplier.
September 18, 2025
Hydrostor has secured US$55 million in funding from Export Development Canada (EDC) to advance development activities for its 200MW/1,600MWh Silver City Energy Storage Centre project in Broken Hill, New South Wales, Australia.
September 17, 2025
China has published a national plan to promote large-scale energy storage facilities, encouraging investment and broader participation in the electricity market.
September 17, 2025
Chinese PV module manufacturer Trina Solar has received the green light from the Victoria government in Australia to build a 500MW/1,000MWh battery energy storage system (BESS).