Battery de-rating risks scaring investors off UK energy storage, Anesco warns

November 17, 2017
LinkedIn
Twitter
Reddit
Facebook
Email
Containerised grid-scale battery energy storage in the UK. Image: Liam Stoker.

UK renewables and battery developer Anesco has warned that the looming de-rating of battery storage in the Capacity Market risks scaring investors away from the technology.

Earlier this year Anesco completed the 10MW Clay Hill Solar Farm, which is the UK’s first subsidy-free solar project. Built alongside 6MW worth of battery storage, the site is hoping to have pre-qualified to participate in the forthcoming Capacity Market auction alongside other battery storage assets.

But the government’s consultation on the proposed de-rating of batteries stands to reduce the levels of support available for battery storage, particularly those of short duration lithium-ion batteries. These changes have been designed to more closely represent the expected duration of batteries in a stress event with all generation technologies currently afforded the same banding, regardless of their duration capability.

The consultation was released in July and could still apply to the forthcoming Capacity Market auctions, although this is considered unlikely. But despite a senior policy advisor at BEIS (the UK government’s Department for Business, Energy & Industrial Strategy), telling an industry event last week that a decision was imminent, there has yet to be any clarity on the issue despite the pre-qualification results being expected within days.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Anesco responded last month by stating that it was investigating the potential to use longer-lasting flow batteries to head off the changes, however chairman Steve Shine has told our UK sister site Clean Energy News that he fears the overhaul could have a more significant impact on investor confidence.

“It’s a negative move at this particular time… it’s not the revenue that investors want, it’s the ability to raise debt and 15-year contracts are vital,” Shine said, adding that one potential remedy would be for the changes to be phased in.

Shine has warned that not only could enforcing the changes wholesale dampen the investment appetite for the technology, but could result in some assets becoming stranded.

“I think there needs to be more joined-up thinking between (transmission system operator) National Grid and BEIS,” he said.

Read Next

December 5, 2025
Developer BrightNight and independent power producer (IPP) Cordelio Power have announced financial close of the 200MW/800MWh Greenwater battery energy storage system (BESS) in Washington state, US.
December 2, 2025
Manoa Energy and HD Renewable Energy Japan have begun commercial operation of a 50MW/104MWh battery storage project in Hokkaido, Japan.
December 1, 2025
European BESS news from project owners Premier Energy Group, Verbund, Eco Stor, Ingrid Capacity, Ric Energy, Ganfeng Lithium, EP Group, RWE and Giga Storage, securing acquisitions, financings and route-to-market (RTM) deals for multiple gigawatts of capacity this past week.
November 26, 2025
Mayor of Greater Manchester Andy Burnham marked the commencement of construction at Highview’s 300MWh liquid air energy storage facility.
November 24, 2025
Developer Akaysha Energy has confirmed that the 850MW Waratah Super Battery will undergo a planned balance of plant shutdown from 20 November to 2 December 2025.