Massachusetts authorities host public comment hearings for 800MWh of battery storage

July 18, 2022
LinkedIn
Twitter
Reddit
Facebook
Email

Developers of two large-scale battery projects in Massachusetts have appeared before the general public at hearings hosted by the state’s Energy Facilities Siting Board (EFSB).

Comprising Medway Grid Battery Storage, a 250MW/500MWh battery energy storage system (BESS) and the Cranberry Point 150MW/300MWh BESS, Public Comment Hearings were held on 13 July and 14 July respectively.

Both projects have asked for special conditions to enable their development from the Energy Facilities Siting Board despite local authority restrictions, requesting for their approval as being in the public interest.

Medway Grid LLC, a company established to develop the project that bears its name, was awarded a 250MW capacity contract by regional electricity network operator ISO New England, to provide capacity in the Southeastern New England capacity zone by June 2024.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Christina Wolf, head of development for the company, noted also that it will make a significant contribution to meeting Massachusetts’ state goal of deploying 1,000MWh of energy storage by 2025. The Commonwealth is targeting net zero greenhouse gas (GHG) emissions from all sectors of its economy by 2050.

While Massachusetts was an early adopter among US states of a policy target for storage (introduced as 200MWh by 2025 in 2017 and later upped), most battery storage development has been focused on solar-plus-storage through the Solar Massachusetts Renewable Target (SMART) scheme with projects much smaller than Medway and Plus Power’s proposals.

The state was also the first in the US to introduce a Clean Peak Standard, which mandates a proportion of peak demand must be met from low emissions sources and more recently is targeting significant offshore wind development off its coast, which would require much greater storage as well as transmission capabilities.

Medway Grid was launched by energy storage developer Able Grid, the development assets of which were bought by infrastructure investor Eolian. Medway Grid submitted a petition to the EFSB in March to construct the standalone BESS facility and a new electric substation, close to an existing transmission corridor and connected directly to the transmission grid via utility Eversource’s substation in Milford Street.

Wetlands expert Marc Bergeron of environmental permitting consultancy Epsilon presented on behalf of Medway Grid that construction on the project site would present limited environmental impact since it is already in-use land that was previously logged for timber.

Other points noted by Bergeron included that there will be no solid or hazardous waste stream from operations and that it will have no impact on vegetated wetlands.

Tesla’s Megapack BESS product has been picked for the project. In terms of fire safety, Wolf said that the project is being designed to meet standards including UL, NPFA and other key certifications and the operator will coordinate any emergency response plans with local fire departments.

Town of Medway town manager Michael Boynton said a draft agreement has been signed with Medway Grid, and that conversations and dialogue around the project to date have been “positive”.

Another town official, Todd Alessandri asked, with the system planned to be largely unmanned and controlled and monitored remotely, how quick response times could be in the event of a fire. Andrew Kaplan, general counsel for Medway, said that in discussion with the local fire chief, the fire department would be notified directly of any incidents and that response times would therefore be “immediate”.

There will be a buffer of space between the battery facility, its infrastructure and existing vegetation, Kaplan said.

Among the first >100MW BESS projects in MA

The next steps will be to get EFSB approval, then the developer will move to get building permitting, go through the town’s Conservation Commission, as well as agreeing financial and business terms with the town authorities.

Boynton noted that Able Grid had approached the town pre-COVID with its proposal for the site, selecting the Milford Street location due to its proximity to transmission lines and the West Medway grid.

However, to go ahead, the project needs to be exempted from local zoning laws. Something similar is happening with developer Plus Power’s Cranberry Point BESS proposal in Carver, another Massachusetts town about 80.5km from Medway.

Both towns have enacted a moratorium on the development of new large-scale battery facilities until zoning laws to properly accommodate energy storage can be introduced, each lasting 11.5 months until March 2023. In the case of Cranberry Point, certain agreements were made to proceed with development before the towns introduced their moratoriums.

Medway Grid general counsel Andrew Kaplan – an attorney with Pierce Attwood – said that as a facility of 100MW or greater classified as a generation asset by ISO New England, state laws mean the development team had to file with the nine-member EFSB for approval. The board includes heads of state environment and land use agencies along with energy industry experts and union representatives.

You can watch both EFSB hearings in full on the Massachusetts Department of Public Utilities Public Hearing YouTube channel, including a broad range of questions from viewers in the local community. Watch the Cranberry Point hearing here and the Medway project hearing here.

24 March 2026
Dallas, Texas
The Energy Storage Summit USA is the only place where you are guaranteed to meet all the most important investors, developers, IPPs, RTOs and ISOs, policymakers, utilities, energy buyers, service providers, consultancies and technology providers in one room, to ensure that your deals get done as efficiently as possible. Book your ticket today to join us in 2026!

Read Next

December 17, 2025
In an upcoming conversation with Energy-Storage.news Premium and Optimisation platform provider Ascend Analytics, CEO Dr. Gary Dorris PhD, discusses the ‘roller coaster’ revenues of the Electric Reliability Council of Texas (ERCOT) market.
December 17, 2025
According to the Q4 2025 US Energy Storage Monitor from Wood Mackenzie Power & Renewables and the American Clean Power Association (ACP), 2025 energy storage installations surpassed 2024 capacity.
December 16, 2025
In this edition of the Energy-Storage.news US news roundup, EticaAG partners with Shell on battery immersion tech, Pacific Northwest National Laboratory begins utility-scale battery testing, and ON.Energy announces a transformer supply agreement.
December 16, 2025
 Utility Georgia Power has reached an agreement with the Public Interest Advocacy (PIA) staff of the Georgia Public Service Commission (PSC), that, if approved, will help lower energy costs and meet electricity demand in the state.
Premium
December 16, 2025
Calibrant’s BESS for a new data centre in Oregon, US, was hailed as the first of its kind, but what are the details beyond the headline? We caught up with Calibrant’s CCO to discuss the practical, commercial and technical specifics of the project.