Ireland’s system operator sets out conditions for 300MW grid services tenders

By David Pratt
LinkedIn
Twitter
Reddit
Facebook
Email
Image: National Grid.

Storage developers eyeing opportunities in Ireland’s DS3 programme will be able to bid for six-year contracts providing frequency response and reserve services in September when transmission system operator EirGrid will launch a new procurement process.

But a number of stipulations have been put in place to cap the volume of applications that could be put forward to limit any expenditure risks identified by the TSO.

The proposed ‘Volume Capped’ procurement process outlined in a consultation published on 29 March sets out which of the DS3 system services will be up included in this year’s auction.

For the full story, visit sister title Clean Energy News.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

11 November 2025
San Diego, USA
The 2024 Summit included innovative new features including a ‘Crash Course in Battery Asset Management’, Ask-Me-Anything formats and debate-style sessions. You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

October 3, 2025
EDF Renewables has brought its 300MWh Milagro project online in New Mexico, while Enlight Renewable Energy has secured US$340 million in tax equity financing for its 940MWh Roadrunner project in Arizona.
October 2, 2025
Solar PV and energy storage firm Canadian Solar has entered into battery storage agreements (BSAs) and long-term services agreements (LTSAs) with Aypa Power for the Elora and Hedley battery energy storage system (BESS) projects in Ontario, Canada.
October 2, 2025
The TSO of Italy has completed its first MACSE auctions for energy storage, procuring 10GWh of capacity at what the NHOA CEO called ‘exceptionally competitive prices’.
October 2, 2025
Quinbrook Infrastructure Partners has completed construction on the first stage of its Supernode battery energy storage system (BESS) in Queensland, Australia.
October 1, 2025
In a recently published interview with Energy-Storage.news Premium, CEO and President of Prevalon Energy, Thomas Cornell, spoke about the global consequences of the budget reconciliation bill.

Most Popular

Email Newsletter