Ireland’s system operator sets out conditions for 300MW grid services tenders

By David Pratt
LinkedIn
Twitter
Reddit
Facebook
Email
Image: National Grid.

Storage developers eyeing opportunities in Ireland’s DS3 programme will be able to bid for six-year contracts providing frequency response and reserve services in September when transmission system operator EirGrid will launch a new procurement process.

But a number of stipulations have been put in place to cap the volume of applications that could be put forward to limit any expenditure risks identified by the TSO.

The proposed ‘Volume Capped’ procurement process outlined in a consultation published on 29 March sets out which of the DS3 system services will be up included in this year’s auction.

For the full story, visit sister title Clean Energy News.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

11 November 2025
San Diego, USA
The 2024 Summit included innovative new features including a ‘Crash Course in Battery Asset Management’, Ask-Me-Anything formats and debate-style sessions. You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

September 3, 2025
During the morning of 30 August 2025, the California Department of Forestry and Fire Protection (CAL FIRE) responded to a possible vegetation fire in the area of independent power producer (IPP) Arevon Energy’s California Flats solar-plus-storage project.
September 3, 2025
910MWh of BESS in Queensland, Australia, has been added to AEMO’s Market Management System, signalling readiness for commissioning.
September 2, 2025
Energy-Storage.news speaks with Karina Hershberg, Associate Principal at engineering firm PAE Engineers, on integrating microgrids with sustainable building design.
September 2, 2025
“The speed at which the grid-forming inverters are operating means that standby consumption will be higher,” said Dave Bowly of AGL.
September 2, 2025
Katherine Hutton, product manager of cybersecurity at Fluence, discusses why cybersecurity is critical for battery storage systems and how to navigate this increasingly complex area.

Most Popular

Email Newsletter