FERC issues preliminary permit for 2.65GW pumped hydro storage plant in Washington

July 20, 2021
LinkedIn
Twitter
Reddit
Facebook
Email
Bad Creek, an existing pumped hydro storage plant in South Carolina. Image: Duke Energy.

A proposed 2,650MW pumped hydro energy storage project in Washington State has received a preliminary permit from the US Federal Energy Regulatory Commission (FERC).

Developer Daybreak Power said yesterday that its US$4.9 billion Halverson Canyon Pumped Storage project received the favourable regulatory decision just before the end of June. The project would be built about 35 miles upstream from the Columbia River’s Grand Coulee Dam and Daybreak said it would enable the integration and delivery of wind and solar power from Montana and other Northwestern areas, delivering electricity to Seattle, Portland and across the region.

Daybreak proposes to build an upper reservoir above Lake Roosevelt, using cheap and surplus renewable energy to pump the water up into it and then drop it through turbines to drive electricity generation when it is most needed. Daybreak did not provide a megawatt-hour figure for capacity but said it would enable the generation of 10 hours of on-demand energy daily, which would put it at at least 26,500MWh.

The project site is planned to minimise disruption to the local environment, local wildlife and population and the developer is working with local stakeholders including landowners, conservation groups and tribes on the planning process.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“Study after study shows we’re going to need massive amounts of storage to integrate high levels of wind and solar, and we need to do it smart. The Halverson Canyon project does that. This project marks a turning point for the Pacific Northwest to transition off fossil resources and onto carbon-free renewables at a scale never seen before,” Daybreak Power CEO Jim Day said.

Daybreak said it is developing a total 50,000MW pipeline of pumped hydro projects. It has made solid proposals for three in total including Halverson Canyon, with the other two being Next Generation Pumped Storage, a 1,540MW facility near Nevada’s Hoover Dam and Navajo Energy Storage Station, a 2,210MW plant near Lake Powell in Arizona.

Pumped hydro developers seek renaissance for legacy clean energy technology

Pumped hydro storage still constitutes the vast majority of the world’s installed electricity storage capacity, despite the recent rapid growth of lithium-ion storage as an option over the past five to seven years. However, despite the low emissions profile and low lifetime cost of energy of pumped hydro, the capital cost of projects and the difficulty of siting large facilities at locations where upper and lower reservoirs can be found or built has been a barrier to new developments for many years.

There appears however to be something of a global renaissance for the technology. The first new pumped hydro project in Australia for nearly 40 years has just gotten underway and in a blog for this site in June, we collected some of the other recent projects under development in countries and regions including Uzbekistan, the UAE, California, Scotland and India.

Within the Pacific Northwest area of the US where Daybreak is developing Halverson Canyon, Energy-Storage.news reported in November 2020 that fund management company Copenhagen Infrastructure Partners (CIP) acquired the Swan Lake 400MW project in Klamath County, Oregon and the 1,200MW Goldendale project in Washington’s Klickitat County. Both are at different stages of development by hydropower developer Rye Developments.

15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

March 26, 2026
Ukraine’s need for energy storage presents opportunities for brave investors, Energy-Storage.news hears from Vadym Utkin, energy storage lead at DTEK.
March 25, 2026
American Battery Factory (AFB) has secured offtake agreements for 4.5GWh of its initial 5.5GWh US factory output.
Premium
March 25, 2026
As battery energy storage systems (BESS) and electric vehicle (EV) infrastructure expand in the US and Europe, a clear contrast is becoming evident in their market growth.
March 24, 2026
The legislative body of Nebraska, US, has advanced a bill to clarify and expand the state’s use of battery energy storage systems (BESS).
March 23, 2026
The New Jersey Board of Public Utilities (NJBPU) has selected developer and IPP Elevate Renewables’ 600MWh battery energy storage system (BESS) for development in Ridgefield, New Jersey, US.