Energy storage developer Eolian has completed an investment in two standalone battery energy storage projects in Texas, which it claims is the first use of the Inflation Reduction Act’s new tax credit incentives (ITC).

Eolian has closed a tax equity investment in the Madero and Ignacio battery storage projects in the city of Mission, Texas, which together total 100MW of nameplate power each and will come online later in 2023. Numerous reports peg their energy storage capacity at 214.5MWh each, or 429MWh in total.

Tax equity investment is a investment structure used to achieve a return based on US federal income tax benefits derived from said investment. Eolian claimed this deal is the first use of the investment tax credit (ITC) for standalone energy storage which came into effect on January 1 as part of the Inflation Reduction Act.

The tax equity investment for the two projects was provided by a fund managed by Churchill Stateside Group, which primarily does real estate financing.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The two battery storage projects are located on the same site and will provide grid reslience in the Rio Grande Valley through trading in the energy market run by Texas’ main grid operator ERCOT.

Alongside being the first use of the new (ITC) Eolian also claimed that together the two projects will constitute the largest “fully-merchant” battery storage projects in the world by energy capacity when they go online.

Typical applications for battery storage in Texas’ ERCOT wholesale electricity market include frequency response services which have historically been a big chunk of battery storage projects’ revenues in the state, regulation reserve service (RRS) and a sub-set within that group called fast frequency response (RRS-FFR).

Eolian’s CEO Aaron Zubaty commented: “This energy storage project is the largest of its kind in the world, represents hundreds of millions of dollars in direct investment by private investors, and solves the problem of meeting demand during hours of high uncertainty that require highly dynamic units that can turn on remotely and instantaneously to keep the lights on. The new face of grid resilience is fast and flexible energy storage to fill the gaps when other resources are too slow or too fragile to meet the challenge.”

The investor was advised by Norton Rose Fulbright LLP for the deal while Churchill Stateside Group was was advised by Husch Blackwell LLP.

ERCOT currently has around 2.7GW of battery storage online at last count, second only to California’s 4.6GW (both figures as of end-2022).

Energy-Storage.news’ publisher Solar Media will host the 5th Energy Storage Summit USA, 28-29 March 2023 in Austin, Texas. Featuring a packed programme of panels, presentations and fireside chats from industry leaders focusing on accelerating the market for energy storage across the country. For more information, go to the website.

15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

June 10, 2026
EDP and SRP complete 200MW/800MWh Arizona BESS, Pathway Power closes $150m facility, and B2U secures Waymo supply deal for second-life EV batteries in grid storage.
June 10, 2026
Gamuda Renewables has secured an interest in the 1,800MWh Hazelwood North solar-plus-storage project in Victoria, Australia.
Premium
June 9, 2026
ESN Premium speaks with Dr Thomas Sisto, of flow battery developer XL Batteries, about using LDES to combat grid strain from heatwaves and data centres.
June 9, 2026
Eku Energy has submitted its 1,000MWh Griffith battery energy storage system (BESS) for environmental assessment under Australia’s EPBC Act.
June 8, 2026
California-headquartered developer esVolta has closed an expanded corporate credit facility providing up to US$450 million of capital to expand new utility-scale energy storage projects in the US.