El Paso Electric elects for 100MW of storage in 370MW capacity push

January 2, 2019
LinkedIn
Twitter
Reddit
Facebook
Email
Image: El Paso Electric via Facebook.

Electricity from 100MW of energy storage facilities will be purchased by US public utility company El Paso Electric, following a competitive solicitation process.

Headquartered in Texas and serving more than 400,000 customers in that state and in New Mexico, the utility determined that it required additional generation and energy management resources in place by the time the 2022 and 2023 summer peaks in electricity demand happen. The utility currently owns around 2,153MW of generation facilities.

El Paso Electric put out its 2017 “All Source Request for Proposals for Electric Power Supply and Load Management Resources” as a consequence, competitively tendering for both the construction of new projects including solar, storage and natural gas and for the purchase of power from third-party owned generation facilities.

Winning proposals remain subject to their obtaining required environmental and construction permits as well as gaining approval from the respective Public Utility Commission of Texas and New Mexico’s Public Regulation Commission. El Paso Electric said the projects chosen and the mix of diverse choices is in line with the need to deploy “cost-effective, diverse and competitive-based energy resources for its customers” in expanding its portfolio, as well as advancing a strategic goal to “remain at the forefront in advancing renewable energy”.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The utility selected:

200MW of utility-scale solar

100MW of energy storage

226MW new natural gas combustion turbine unit at existing power station

50MW to 150MW of wind and solar power purchases

The 2022-2023 peak period is defined as between 1 May 2022 and 1 May 2023, while the RFP called for 50MW of new generation capacity by 2022 and 320MW of generation capacity by 2023. Bids were received by October this year and resources types eligible to participate were ‘conventional intermediate generation with cycling capability, ‘renewable energy – preferable dispatchable or easily curtailed from outputting to the grid’, and ‘load management’, in addition to ‘energy storage’. The document did not differentiate between types of energy storage, whether batteries or otherwise. The planned gas power plant has an anticipated cost of US$143 million and is expected to be operational by the latter date.

In mid-December, El Paso Electric also issued an RFP for a feasibility study for a utility-scale solar-plus-storage project to supply New Mexico State University facilities as well as providing an educational and research facility for students from the real-world application of distributed energy technology. The RFP calls for a solar project of up to 3MW.

15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

March 31, 2026
The Michigan Public Service Commission has approved six battery energy storage system (BESS) projects totalling 1,332MW of capacity in the US state.
March 31, 2026
In this news roundup, Unigrid, Inlyte Energy, CIUDEN, and Sunamp are advancing non-lithium energy storage technologies worldwide.
March 30, 2026
Chile continues to be Latin America’s hotspot for energy storage deployments, with a major new deal for Grenergy and Engie bringing a project online in the past week.
March 27, 2026
IPP Akuo will soon start building a 2.75-hour BESS project in Borba, Portugal, integrated into its 181MW Santas solar PV plant.
March 26, 2026
esVolta has closed a US$139.6 million project financing package with MUFG Bank for its 300MWh Boxcar energy storage project in Texas, US.