€20m grant funding for Namibia’s first grid-scale BESS from Germany’s national development bank

LinkedIn
Twitter
Reddit
Facebook
Email
NamPower managing director Kahenge S Haulofu, National Planning Commission director general Obeth Kandjoze and KfW’s Barbara Pirich at a signing ceremony earlier this month. Image: NamPower via LinkedIn.

A grant of €20 million (US$22.66 million) has been made to Namibia’s government-owned electric utility company for the development of the African country’s first grid-scale battery storage project. 

Namibia Power Corporation (NamPower) told Energy-Storage.news that through a bilateral cooperation agreement between the federal German government and the Republic of Namibia, Germany’s KfW development bank has made the funding available. 

It will go towards the construction of a 58MW / 72MWh battery energy storage system (BESS) at Omburu substation in Namibia’s western Erongo region. 

It will perform a number of applications for NamPower: peak load shifting, energy arbitrage, emergency back up power provision, ramp-rate control of power plants and reactive power control. 

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

NamPower will contribute around 20% of the total project costs, paying for transmission interconnection and local duties and taxes not covered by the grant funding. 

The Omburu BESS will contribute to the expansion of renewable energy in the region by storing locally generated renewable power as well as electricity imported from the Southern African Power Pool (SAPP), which can charge the battery at cheaper, off-peak times, and then the energy can be discharged during peak times. 

This would also offset the use of energy from the 120MW Van Eck Power Station, Namibia’s only coal-fired power plant, which as the utility pointed out is now ageing, having been built in the early 1970s. 

The BESS will also be used to load-follow local renewable energy generation, helping to stabilise the grid as it accepts the variable output of solar or wind plants. 

Finally, it will also enable Namibia to increase its participation in energy trading with the 11 other member states of the SAPP, helping to lower overall emissions across the pool. 

Namibia has a National Energy Policy target of sourcing 80% of its energy from local sources by 2023 and a Renewable Energy Policy target of 70% by 2030. The BESS will contribute to meeting both of these, as well as helping lower overall cost of energy that consumers pay, NamPower managing director Kahenge S Haulofu said. 

“As one of the first utility-scale storage projects in Southern Africa, the Namibia battery storage project BESS can be described as a flagship project,” Barbara Pirich, KfW’s country director for Namibia said at a signing ceremony held earlier this month.

“As the project is the first of its kind in Southern Africa, it fulfils a pioneering function – it is expected that subsequent projects in the same field will benefit substantially from the experience gained from his project.”

3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.

Read Next

September 11, 2026
Our collection of user-posted analysis, views, and unofficial news, gathered from our networks on LinkedIn, returns for its third outing.
September 11, 2026
Swedish multinational power company Vattenfall has taken a final investment decision (FID) to proceed with a 254MW/1,000MWh battery storage project in Germany.
September 7, 2026
Pakistan’s National Electric Power Regulatory Authority (NEPRA) has approved plans to require bidders in a renewable energy auction to include energy storage.
September 7, 2026
Blueleaf Energy and Universal Peak have closed financing for a 100MW/400MWh battery storage project, which was one of four winning bids in a Malaysian government tender.
September 3, 2026
Bulgaria now has a world-leading amount of battery storage capacity relative to energy system despite a period of political turnover, although those assets are now cannibalising the revenues which attracted investment in the first place.