€20m grant funding for Namibia’s first grid-scale BESS from Germany’s national development bank

December 24, 2021
LinkedIn
Twitter
Reddit
Facebook
Email
NamPower managing director Kahenge S Haulofu, National Planning Commission director general Obeth Kandjoze and KfW’s Barbara Pirich at a signing ceremony earlier this month. Image: NamPower via LinkedIn.

A grant of €20 million (US$22.66 million) has been made to Namibia’s government-owned electric utility company for the development of the African country’s first grid-scale battery storage project. 

Namibia Power Corporation (NamPower) told Energy-Storage.news that through a bilateral cooperation agreement between the federal German government and the Republic of Namibia, Germany’s KfW development bank has made the funding available. 

It will go towards the construction of a 58MW / 72MWh battery energy storage system (BESS) at Omburu substation in Namibia’s western Erongo region. 

It will perform a number of applications for NamPower: peak load shifting, energy arbitrage, emergency back up power provision, ramp-rate control of power plants and reactive power control. 

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

NamPower will contribute around 20% of the total project costs, paying for transmission interconnection and local duties and taxes not covered by the grant funding. 

The Omburu BESS will contribute to the expansion of renewable energy in the region by storing locally generated renewable power as well as electricity imported from the Southern African Power Pool (SAPP), which can charge the battery at cheaper, off-peak times, and then the energy can be discharged during peak times. 

This would also offset the use of energy from the 120MW Van Eck Power Station, Namibia’s only coal-fired power plant, which as the utility pointed out is now ageing, having been built in the early 1970s. 

The BESS will also be used to load-follow local renewable energy generation, helping to stabilise the grid as it accepts the variable output of solar or wind plants. 

Finally, it will also enable Namibia to increase its participation in energy trading with the 11 other member states of the SAPP, helping to lower overall emissions across the pool. 

Namibia has a National Energy Policy target of sourcing 80% of its energy from local sources by 2023 and a Renewable Energy Policy target of 70% by 2030. The BESS will contribute to meeting both of these, as well as helping lower overall cost of energy that consumers pay, NamPower managing director Kahenge S Haulofu said. 

“As one of the first utility-scale storage projects in Southern Africa, the Namibia battery storage project BESS can be described as a flagship project,” Barbara Pirich, KfW’s country director for Namibia said at a signing ceremony held earlier this month.

“As the project is the first of its kind in Southern Africa, it fulfils a pioneering function – it is expected that subsequent projects in the same field will benefit substantially from the experience gained from his project.”

Read Next

April 13, 2026
Brazil’s national regulator, ANEEL, postponed an important decision on energy storage, days after approving the country’s first hybrid plant.
April 9, 2026
Maxxen managing director Ruben Valiente speaks with Energy-Storage.news editor Andy Colthorpe at Energy Storage Summit 2026 in London.
April 8, 2026
IPPs Zelestra, BNZ and ALFI have secured offtake and financing to hybridise solar projects with BESS across Spain, Italy, Portugal and Romania. 
Premium
April 2, 2026
MetaWealth COO Michael Topolinski IV discussed the firm’s first BESS project in Romania, which is partially financed with bonds marketed at retail investors. 
April 1, 2026
Developer-investor Hexa Energy Services has inaugurated what is thought to be Japan’s first operational battery storage project with a capacity market contract.