Publicly-owned energy company CleanCo Queensland has officially opened the Swanbank battery energy storage system (BESS), a 250MW/500MWh facility located at the former Swanbank coal power station site in Ipswich, Australia.

The project, located approximately 45km south-west of Brisbane, will play a major role in repurposing retired coal-fired generation infrastructure into a modern clean energy hub.

The Swanbank Battery, registered with the Australian Energy Market Operator (AEMO) and commencing testing and commissioning in October 2025, has a 2-hour duration storage capacity.

The project is located at the Swanbank B site, which was originally commissioned in 1971 with four 120MW coal-fired steam turbines and decommissioned in 2012.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

By reusing existing transmission infrastructure, the Swanbank Battery has been integrated into the National Electricity Market (NEM) more quickly and cost-effectively. The system connects to the grid via a new 275kV substation, utilising the established transmission connections that previously served the coal-fired power station.

Queensland’s treasurer and minister for energy, David Janetzki, emphasised the importance of the Swanbank Battery in advancing Queensland’s energy infrastructure.

“This grid-scale battery is exactly the kind of modern infrastructure our Energy Roadmap is designed to deliver—technology that keeps the lights on, supports renewables, and strengthens reliability for Queenslanders,” Janetzki said.

“At Swanbank, we can see how batteries and gas generation work together to support system reliability, particularly during peak demand periods.”

The AU$330 million (US$214 million) project was funded through the Queensland Renewable Energy and Hydrogen Jobs Fund. Tesla supplied its Megapack battery solution, while Yurika provided infrastructure and installation services.

CleanCo CEO Tom Metcalfe highlighted the project’s role in the company’s broader mission to deliver reliable, lower-emission energy.

“The Swanbank Battery is a critical addition to CleanCo’s portfolio, providing greater flexibility to supply reliable, lower-emissions energy to our customers when it’s needed most,” Metcalfe said.

“This project reflects the continued evolution of the Swanbank site, from coal to gas-fired stations and now battery storage, reinforcing CleanCo’s role in supporting Queensland’s energy system with dependable, lower-emission firming generation.”

The Swanbank site is set to become a clean energy hub, with potential future developments including wind, solar, hydrogen production and additional energy storage capacity.

The Energy Storage Summit Australia 2026 will be returning to Sydney on 18-19 March. It features keynote speeches and panel discussions on topics such as the Capacity Investment Scheme, long-duration energy storage, and BESS revenue streams. ESN Premium subscribers receive an exclusive discount on ticket prices. 

To secure your tickets and learn more about the event, please visit the official website. 

26 November 2026
9am GMT / 1pm GST
In this webinar, Florian Didier and Salomé Perperot from Clean Horizon share the approach they use when supporting IPPs through optimiser selection and contract negotiation across Europe. The presentation will be followed by a live Q&A session in which attendees can put their own questions to the speakers. Who should attend: IPPs and developers, asset owners and investors, lenders and financial advisors, and anyone involved in the commercial structuring of battery storage projects.
22 February 2027
InterContinental London - The O2, London, UK
The Future of Energy Storage Starts Here Three days in London where developers, IPPs, investors, utilities and the manufacturers building the technology come to close deals, not swap business cards. If you need to be in the room with the people deploying capital into European storage, this is that room.

Read Next

November 13, 2026
US distributed energy resource (DER) installer Sunrun has announced a preferred equity investment with energy investment firm Captona.
November 13, 2026
Another edition of our BESS Industry Buzz, this week looking at new details on CATL’s sodium-ion technology, BESS availability, BAAJA trade-offs and the price of speed to power.
November 13, 2026
West Arthur Energy, a project company owned by Western Australian developer Lacour Energy, has referred a wind generation site with a 4,000MWh battery energy storage system (BESS) to Australia’s EPBC Act.
November 12, 2026
AirTrunk has signed an exclusivity agreement with European Energy Australia covering more than 800MWh of battery storage in NSW.
November 12, 2026
As data centre demand surges, utilities and developers are turning to distributed energy resources (DERs) to ease grid strain.