CleanCo opens 500MWh Tesla Megapack BESS in Queensland, Australia

LinkedIn
Twitter
Reddit
Facebook
Email

Publicly-owned energy company CleanCo Queensland has officially opened the Swanbank battery energy storage system (BESS), a 250MW/500MWh facility located at the former Swanbank coal power station site in Ipswich, Australia.

The project, located approximately 45km south-west of Brisbane, will play a major role in repurposing retired coal-fired generation infrastructure into a modern clean energy hub.

The Swanbank Battery, registered with the Australian Energy Market Operator (AEMO) and commencing testing and commissioning in October 2025, has a 2-hour duration storage capacity.

The project is located at the Swanbank B site, which was originally commissioned in 1971 with four 120MW coal-fired steam turbines and decommissioned in 2012.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

By reusing existing transmission infrastructure, the Swanbank Battery has been integrated into the National Electricity Market (NEM) more quickly and cost-effectively. The system connects to the grid via a new 275kV substation, utilising the established transmission connections that previously served the coal-fired power station.

Queensland’s treasurer and minister for energy, David Janetzki, emphasised the importance of the Swanbank Battery in advancing Queensland’s energy infrastructure.

“This grid-scale battery is exactly the kind of modern infrastructure our Energy Roadmap is designed to deliver—technology that keeps the lights on, supports renewables, and strengthens reliability for Queenslanders,” Janetzki said.

“At Swanbank, we can see how batteries and gas generation work together to support system reliability, particularly during peak demand periods.”

The AU$330 million (US$214 million) project was funded through the Queensland Renewable Energy and Hydrogen Jobs Fund. Tesla supplied its Megapack battery solution, while Yurika provided infrastructure and installation services.

CleanCo CEO Tom Metcalfe highlighted the project’s role in the company’s broader mission to deliver reliable, lower-emission energy.

“The Swanbank Battery is a critical addition to CleanCo’s portfolio, providing greater flexibility to supply reliable, lower-emissions energy to our customers when it’s needed most,” Metcalfe said.

“This project reflects the continued evolution of the Swanbank site, from coal to gas-fired stations and now battery storage, reinforcing CleanCo’s role in supporting Queensland’s energy system with dependable, lower-emission firming generation.”

The Swanbank site is set to become a clean energy hub, with potential future developments including wind, solar, hydrogen production and additional energy storage capacity.

The Energy Storage Summit Australia 2026 will be returning to Sydney on 18-19 March. It features keynote speeches and panel discussions on topics such as the Capacity Investment Scheme, long-duration energy storage, and BESS revenue streams. ESN Premium subscribers receive an exclusive discount on ticket prices. 

To secure your tickets and learn more about the event, please visit the official website. 

3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.

Read Next

October 2, 2026
Outgoing California Governor Gavin Newsom recenty addressed approximately 1,200 bills, including several energy storage and solar related bills that were either approved or vetoed.
October 2, 2026
Fu-Gen has sold a 100MW ready-to-build battery storage project in Finland to Nala Renewables, extending their Nordic BESS pipeline to 275MW.
October 2, 2026
NSW’s IPC has approved BayWa r.e.’s Bullawah Wind Farm, pairing 804MW of wind with a 718MWh battery in the South West REZ.
October 1, 2026
Battery energy storage systems (BESS) are increasingly being positioned as essential infrastructure investments rather than purely financial assets, as seen in a series of strategic partnerships announced in late September that integrate storage with broader energy and digital infrastructure strategies.
October 1, 2026
Energy-Storage.news spoke with Noemí Gallardo, Commissioner at the California Energy Commission (CEC), at the US Solar & Storage Finance event in Garden Grove, California, about the growth of BESS within the state.