RMI’s Sunshine For Mines team released a report alongside BHP analysing renewable energy potential at legacy mines. Credit: RMI

Melbourne-headquartered mining giant BHP, in partnership with the Rocky Mountain Institute (RMI), has projected 500MW of potential capacity combining solar, wind and energy storage at its old North American mining sites.

Solar PV was seen as having the highest potential at these closed or legacy mining sites with some potential for combination with energy storage. There were also a few areas where wind energy was also deemed most suitable.

RMI’s Sunshine For Mines (SfM) team released a report alongside BHP, named ‘New Lives for Old Mines: A Method for Developing Renewable Energy at Closed Mine Sites’.

Most major storage technologies are covered by SfM’s analysis, including pumped hydro, chemical (Lithium-ion for example) and kinetic (flywheels for example).

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

SfM said: “Many saturated energy markets, such as California, have a large demand for storage to help with production and load balancing. Similarly, flywheels are maturing as a technology and can be a great grid-balancing and loadshifting storage option.”

The teams have used an exhaustive methodology to analyse how legacy mines can be turned into independent power plants, storage facilities, or value-added grid-service providers. This would offer new revenue streams for redundant or inactive mines, which are often long-term liabilities for mining operators as they have to continue maintaining the sites after closure. Options for reusing mining sites are also constrained by contamination from the previous mining activity.

SfM screens mining sites and creates a environmental, permitting, and regulatory scorecard, before investigating the potential LCOE’s of various renewable energy technologies at each location.

In a brief RMI noted: “Innovations are also available around market access. For example, even in areas where no market is available, creative solutions such as wheeling the offtake to the CAISO deregulated market in California or entering into purchase agreements with local cooperatives may be possible. These solutions are feasible from a technical and regulatory perspective, and specific opportunities along these lines can be further explored.”

Ultimately the aim is to transform “legacy sites from liabilities into assets”, according to RMI.

Late last year, BHP showed clear interest in installing solar-plus-storage applications for its own remote operations, as similar project plans were announced in Australia.

3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.

Read Next

September 22, 2026
Residential battery energy storage systems (BESS) across California discharged more than 580MW of peak power to the state’s grid on the evening of 9 September 2026 via a Tesla-Sunrun VPP.
September 22, 2026
Utility PG&E has selected six new California microgrid projects for a US$30 million investment, while Massachusetts’ Department of Energy Resources is awarding US$40 million across 36 BESS projects.
September 16, 2026
Recent moves from the US federal government could prove more damaging to US renewable energy deployment than foreign entity of concern (FEOC) compliance requirements, according to legal and industry experts.
September 11, 2026
Greek renewables developer Metlen Energy & Metals has signed an agreement with utility Copec for the sale of the Tamarico II solar-plus-storage project in Chile’s Atacama region.
September 7, 2026
Tech giant Google, Tesla, utility Pacific Gas and Electric (PG&E), and distributed energy resource (DER)-focused company Sunrun are launching a new virtual power plant (VPP) in California, US.