BESS price falls pushing marginal projects into IRR investors need, US developer says

March 28, 2024
LinkedIn
Twitter
Reddit
Facebook
Email

BESS price falls have pushed many marginal projects in merchant markets into a rate of return needed for investment, US developer Available Power told Energy-Storage.news amidst the sale process for its own 100MW/200MWh ERCOT project.

The falling prices of BESS over the course of the last 6-12 months has been well-documented by Energy-Storage.news recently, and Available Power’s president Ben Gregory said this has significantly boosted the market for projects in merchant markets (like Texas, where ERCOT is the grid operator).

“A lot of M&A slowed down and then picked up once lithium and BESS prices came down, because a lot of projects that were on the margins for IRR (internal rate of return) became more attractive,” Gregory said, speaking in an interview at Solar Media’s Energy Storage Summit USA 2024 in Austin, Texas’ state capital, last week.

“A project that was at 12% IRR last year, is now at 14-15% IRR because of the BESS price falls, and has now been pushed to the rate investors need for merchant assets. So you will see a lot more activity. The price decreases have had a tremendous impact on what we’re doing.”

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The president of system integrator Powin alluded to this type of IRR-dependent project in comments to Energy-Storage.news included in a previous article.

Company’s 200MWh project hits NTP and enters sales process

M&A activity has subsequently picked up, especially in the 9.9MW/20MWh asset class – a size of project in ERCOT which benefits from a much quicker interconnection process due to being below a 10MW threshold – Gregory said, saying the firm recently sold three assets this size. Part of this is also down to an increased level of education from investors about energy storage, he added.

Alongside its portfolio of 9.9MW/20MWh projects, Available Power has developed a much larger 100MW/200MWh project near Austin, at a new airline and technology centre development called Greenport.

Gregory said the Greenport BESS project has reached notice to proceed (NTP) and is currently being sold by the company, though its commercial operation date (COD) had to be pushed back substantially from the mid-2024 initial target.

“Greenport is at NTP, and we’re currently selling the project. We are running an auction process, in coordination with (project M&A marketplace) LevelTen Energy, and have substantial interest in part because of the tolling agreement options that have recently emerged in the market,” Gregory said.

“What made it tough to sell last year was the uncertainty and long-lead times on the equipment supply, especially on circuit breakers, so we secured our own supply of equipment to achieve a commercial operation date (COD) of February 2026. That was a painful exercise, but was necessary in order to meet investors’ requirements.”

‘Manufacturing’ approach to development in face of falling prices

Energy-Storage.news then asked Gregory how the firm was dealing with reportedly falling prices for NTP projects in the US market. Speaking with Energy-Storage.news in November, and specifically mentioning 5-20MW projects and the Texas market, developer-operator Agilitas Energy’s CEO Barrett Bilotta said prices being asked for some portfolios of NTP projects had plummeted by 70% year-on-year.

In response to the question of project pricing, Gregory said that Available Power is taking a “manufacturing-like, standardised approach to development”.

Gregory: “We know what buyers want versus trying to accommodate or anticipate everyone’s hypothetical requirements. By dialling in on a specific set of requirements, we might leave some money on the table but we can do much more volume.”

Speaking at last year’s Summit event in Austin, Available Power’s VP business development Alex Krass explained how Available Power has an engineering, procurement and construction (EPC) partnership with substation specialist Linxon to build projects once they transact.

Discussing the BESS pricing fall, Gregory added that supply from China was “attractive” but that products from other countries are nearing parity. Consultancy Clean Energy Associates (CEA) forecasted in October 2023 that the Inflation Reduction Act’s incentives would make US-manufactured BESS cost-competitive with China’s by 2025.

24 February 2026
InterContinental London - The O2, London, UK
This isn’t just another summit – it’s our biggest and most exhilarating Summit yet! Picture this: immersive workshop spaces where ideas come to life, dedicated industry working groups igniting innovation, live podcasts sparking lively discussions, hard-hitting keynotes that will leave you inspired, and an abundance of networking opportunities that will take your connections to new heights!

Read Next

Premium
November 26, 2025
Energy-Storage.news Premium speaks with Michael Kirschner, Managing Director, US, for Habitat Energy, about optimising BESS projects in ERCOT.
Sponsored
November 26, 2025
As Australia accelerates its transition toward renewables, demand for reliable & sustainable energy storage solutions has never been higher.  
November 25, 2025
Texas-based IPP Vistra Energy has informed the California Energy Commission (CEC) that it will not be advancing its 600MW Morro Bay battery energy storage system (BESS).
November 25, 2025
San Diego-based home battery storage company NeoVolta has entered into agreements for a US$13 million private placement financing anchored by Infinite Grid Capital (IGC).
November 24, 2025
Developer Akaysha Energy has confirmed that the 850MW Waratah Super Battery will undergo a planned balance of plant shutdown from 20 November to 2 December 2025.