Developer: fewer eyes on 9.9MW ‘distributed play’ segment of ERCOT storage market

LinkedIn
Twitter
Reddit
Facebook
Email

Developer Available Power is focusing on the ‘distributed play’ of 9.9MW-or-less battery storage opportunities within the area of grid operator ERCOT in Texas, a senior executive told Energy-Storage.news.

The company was set up in 2020 by ex-Shell executives and has initially focused on the ERCOT market to “get really good in one space”, VP business development Alex Krass said, as well as ensure it gets projects on the ground before the market begins to saturate.

Battery storage projects in the ERCOT interconnection queue have reached the high double-digit gigawatts of capacity since the Inflation Reduction Act was passed. Most projects in the queue will likely not get built and Available Power has two main strategy pillars in place to ensure its projects, which it sells at notice-to-proceed (NTP) stage, see the light of day.

The first is focusing on smaller projects of 9.9MW while the second is bringing in an engineering, procurement and construction (EPC) partner Linxon to deliver on the project after it is sold to a buyer at NTP. The second pillar means it generally looks to sell to traditional financial institutions rather than those with existing EPC relationships.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Speaking to Energy-Storage.news while attending the Energy Storage Summit USA in Austin last month, Krass said the distributed play approach has a few advantages: “One, you can skip a part of the interconnection process with ERCOT (with projects under 10MW) so your time to market is quicker, which is fantastic. Secondly, the data on distribution substations and capacity and locations is harder to come by than for transmission data, so there are fewer eyes on those smaller, distributed scale opportunities.”

On the second pillar, Krass claimed that most developers selling at NTP – otherwise known as a ‘develop and flip’ model – are focusing primarily on getting projects ready to sell and then are “done with it”.

“I think we, on the other hand, have attention to detail around what’s going to be a good project over 20 years. With that, location becomes key, and who you partner with to bring them to COD (commercial operation date) becomes key. And so for us the Linxon relationship is fantastic because they’re really the ones who take the ball once it hits NTP and bring it to COD.”

“We sell the projects at NTP but with the Linxon relationship, we have the contracts, the equipment procured and everything in place, so it’s sort of a turnkey approach to the asset buyer who doesn’t need to bring any of that themselves. They just sign on the dotted line and provide the capital to bring it to fruition. So we’re looking more for the traditional financial capital partners versus someone who might have an EPC relationship or have an equipment relationship.”

“And while we don’t necessarily take an active role post-NTP, we have teed all of that up to bring it to COD, and believe we’re picking the right partners and have the right contracting mechanisms in place to ensure that the assets don’t just stay in the queue and drop out but actually get into operation.”

Available Power has 300MW/600MWh of near-term projects which it expects to reach NTP this year and COD in 2024, comprised of a 100MW/200MWh project near Austin and ten 9.9MW projects (the firm still does larger projects on an ‘opportunistic basis’, Krass said). Its total pipeline is over 1GW.

“Two hour duration is the sweet spot. A lot of the PUCTs (Public Utilities Commission of Texas) regulations coming in are incentivising the 2-hour-plus duration, but going to three or four you really get hammered on the Capex,” Krass added.

The question of whether or when the ERCOT market would saturate was a big talking point at the two-day event in Austin, and Energy-Storage.news will be publishing a more in-depth piece with multiple views on it in the coming weeks.

20 April 2027
Renaissance Dallas at Plano Legacy West Hotel, Dallas, Texas, Dallas
Policy, Procurement and Power Demand: Defining the Next Chapter for Energy Storage. Two days in Dallas where developers, IPPs, investors, utilities and the manufacturers building the technology come to close deals, not swap business cards. If you need to be in the room with the people deploying capital into US storage, this is that room.

Read Next

November 20, 2026
Sodium-ion (Na-ion) is continuing to gain traction as a legitimate “major chemistry” — with CATL, BYD, and GM all committing to it — some developers, within and outside the US Na-ion space have argued that greater policy support should be directed toward advancing the technology.
November 20, 2026
EDF power solutions Australia has acquired the 250MW Holloway BESS project in New South Wales (NSW) from developer SynCo Global.
November 20, 2026
Australia committed a record 2.4GW of renewable energy projects to construction in the third quarter of 2026, while battery energy storage systems (BESS) committed in the quarter covered 13% of the new storage capacity needed by 2030.
Premium
November 19, 2026
As AI-driven data centre demand reshapes the US power landscape, BESS technology providers at RE+ highlighted an unexpected competitive advantage.
Sponsored
November 19, 2026
Pressure-sensitive adhesive (PSA) tape suppliers are testing dielectric materials for BESS lifetimes of 30 years or more, as rising pack voltages push tracking performance requirements higher.