AES to install largest battery-based energy storage project in US for SDG&E

August 19, 2016
LinkedIn
Twitter
Reddit
Facebook
Email

AES will deploy its Advancion 4 storage systems at two SDG&E substations in San Diego County, California, with 30MW in Escondido and 7.5MW in El Cajon. Credit: AES
US-based storage provider AES Energy Storage, a subsidiary of AES Corporation, has signed contracts with utility San Diego Gas and Electric (SDG&E) to install two energy storage arrays with a combined capacity of 37.5MW.

AES will deploy its Advancion 4 storage systems at two SDG&E substations in San Diego County, California, with 30MW in Escondido and 7.5MW in El Cajon. They will help the utility improve regional reliability and integrate more renewable energy. The Advancion arrays will be able to provide 37.5 MW of power for four continuous hours and serve as a 75 MW of flexible resource to the grid.

The systems will include batteries by Samsung SDI and power conversion systems by Parker Hannifin.

The projects will become operational by the end of January 2017 and the Escondido array will be the largest battery-based energy storage project in operation in the US, according to AES.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The utility is trying to accelerate its uptake of energy storage with support from the California Public Utilities Commission (CPUC).

Andrés Gluski, AES president and chief executive, said: “We are excited that SDG&E has selected AES’ Advancion energy storage solution to help meet peak demand and ensure the reliability of the electric grid in Southern California. AES recently made Advancion available to utilities, developers and commercial customers interested in owning our innovative and scalable solution.”

James Avery, SDG&E’s chief development officer, said: “These batteries are beneficial because they maintain a reliable flow of energy to customers when they need it most. We also are national leaders in supplying renewable resources, with more than 33% of the energy we supply to customers coming from wind and solar. These batteries will help smoothly integrate this growing supply of clean energy onto the power grid for use by our customers.”

AES Energy Storage recently made significant expansions away from established markets into relatively untapped regions across the globe.

24 March 2026
Dallas, Texas
SolarPLUS USA brings together the developers, investors, utilities, and system operators shaping the next phase of America’s clean energy build-out. As solar, storage, and hybrid technologies rapidly converge, the Summit provides a focused platform to tackle grid constraints, revenue optimisation, project financing, and the commercial models defining firm, flexible renewable power. Join us to explore the opportunities and challenges driving the Solar+ era across the US market.
15 April 2026
Milan Marriott Hotel, Italy
Solarplus Europe 2026 marks the evolution of Europe’s longest-running solar conference, reflecting the industry’s transition from standalone PV to fully integrated solar-plus-storage and hybrid energy systems. Taking place in Milan, the Summit will unite developers, investors, policymakers, and technology leaders to explore how Europe can deliver firm, flexible, and bankable renewable power at scale. With a sharp focus on system integration, storage deployment, hybrid project design, and market-ready business models, Solarplus Europe provides the platform for shaping the next phase of the continent’s solar and clean power build-out.

Read Next

February 12, 2026
Tesla is set to officially launch its first vehicle-to-grid (V2G) programme in Texas, US, soon with eyes to expand into California.
February 11, 2026
Energy storage developer NineDot Energy closes US$431 million in construction financing for New York BESS projects. Meanwhile, US energy efficiency and renewables company Ameresco completes multiple tax credit transfer and financing transactions for solar PV and BESS.
February 9, 2026
Software-focused battery energy storage system (BESS) integrator FlexGen has put two utility-scale BESS projects in operation in Wisconsin and Iowa, US, totalling 700MWh.
Premium
February 5, 2026
That was the view of Søren Juel Hansen, energy storage director at Nordic Solar, when asked by Energy-Storage.news about the role of transmission system operators (TSO) in the industry. 
February 4, 2026
IPP Enlight Renewable Energy has reached development milestones for its total 1.21GW solar plus 4GWh energy storage CO Bar Complex in Arizona, US, and is now advancing the project toward operation.