US IPP BrightNight gets grid connection approval for Australia hybrid solar project

LinkedIn
Twitter
Reddit
Facebook
Email

The Australian Energy Market Operator (AEMO) has granted US independent power producer (IPP) BrightNight approval to connect its Mortlake Energy Hub, which includes solar and storage facilities, to the Victoria grid.

The project is BrightNight’s first hybrid renewable power project in Australia, and consists of a 360MW solar farm alongside a 300MW battery energy storage system (BESS), which will account for more than 1% of the state’s total electricity consumption. The company plans to begin construction at the project in 2025.

“Australia’s increasing energy demand, alongside that of the broader region, presents vast opportunities for us to provide our cutting-edge renewable energy solutions to drive the adoption of clean energy,” said Jerome Ortiz, BrightNight APAC CEO.

Projects such as these will help Victoria meet its renewable power generation targets, which include the goal of renewable power accounting for 40% of the state’s electricity generation share by 2025. Victoria is well on track to meet this target – the share of renewable power in the state’s energy mix has increased from 12.2% in 2013-14 to 37.8% in 2022-23 – and currently has over 1GW of utility-scale solar capacity in operation, with more than 5.3GW of capacity approved and a further 190MW of capacity currently under construction.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The Mortlake project will also help meet the state’s energy storage goals, with the government aiming to install 6.3GW of energy storage capacity by 2035. Planning documents submitted by BrightNight to the Victorian government note that the Mortlake project will meet up to 11% of the state’s 2030 storage capacity target, and up to 5% of the state’s 2035 storage capacity target.

To read the full version of this story, visit PV Tech.

Read Next

October 1, 2025
Dr Mahdi Behrengrad, head of energy storage at Pacifico Energy, speaks to Energy-Storage.news ahead of next week’s Energy Storage Summit Asia 2025 in Manila.
September 30, 2025
A renewable energy subsidiary of oil & gas company Reservoir Link has agreed to jointly develop the first dispatchable solar PV power plant in Malaysia.
September 30, 2025
Australia’s National Electricity Market (NEM) achieved multiple battery energy storage records during the weekend of 27-28 September 2025, highlighted by total storage capacity reaching 6,591.5MWh for the first time.
September 25, 2025
Victoria has become the first state in Australia’s National Electricity Market (NEM) to achieve more than 1GW of simultaneous battery storage charging.
September 24, 2025
Two battery storage offtake agreements have been signed in Australia, representing over 2GWh of storage capacity.

Most Popular

Email Newsletter