UK solar investor Foresight enters battery storage fray with 35MW project purchase

LinkedIn
Twitter
Reddit
Facebook
Email
RES battery installations for frequency response near Chicago. Image: RES.

UK-based infrastructure investor Foresight Group has sealed its maiden battery storage purchase, acquiring the 35MW RES-built Port of Tyne project in the North-East of England.

The project – one of eight battery storage installations to receive a National Grid Enhanced Frequency Response contract while also being successful in this year’s capacity market auction – will become the latest addition to Foresight’s renewables infrastructure portfolio which already crosses the solar and energy from waste sectors.

Construction of the project will start immediately and it is expected to come on stream early next year.

Foresight revealed it was edging closer to its first battery storage play earlier this year and Dan Wells, partner within Foresight’s infrastructure team, heralded the technology’s potential to offer up interesting investment opportunities.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Project ‘sets exciting precedent for the integration of battery storage into the UK energy system’

At that time he spoke of the need for a diverse mix of revenue streams to make utility-scale battery storage feasible from an investment perspective, and today spoke of the technology’s contribution to the wider energy transition.

“The acquisition consolidates Foresight’s position as a leader in investing both in renewable energy generation and the flexible grid infrastructure required to accommodate increasing penetration of renewables, such as energy storage.

“We are delighted to have worked alongside RES (Renewable Energy Systems) to reach financial close on this pioneering project which sets an exciting precedent for the integration of battery storage into the UK energy system,” Wells said.

Meanwhile Rachel Ruffle, managing director at RES, said that the company looked forward to building and operating the Port of Tyne project on Foresight’s behalf.

Foresight used funds from its inheritance tax solution (ITS) to finance the purchase and was advised by Osborne Clarke.

It is not the first EFR-supported battery storage project to exchange hands however. Italian power company Enel snapped up Element Power’s 12.5MWh project last month, joining the likes of major international utilities EDF and Vattenfall who will own and operate National Grid-supported projects once they’re complete.

13 October 2026
London, UK
Now in its second edition, the Summit provides a dedicated platform for UK & Ireland’s BESS community to share practical insights on performance, degradation, safety, market design and optimisation strategies. As storage deployment accelerates towards 2030 targets, attendees gain the tools needed to enhance returns and operate resilient, efficient assets.

Read Next

May 21, 2026
The UK’s NESO has cleared 150GW of BESS from its grid connection queues, according to figures from BloombergNEF.
May 21, 2026
Singapore-based Equis has launched GreenPoint Energy, a wholly owned subsidiary consolidating its Australian renewable energy and battery storage operations under a dedicated platform with a 2.5GW portfolio of 12 battery energy storage systems (BESS) and wind projects across every National Energy Market (NEM)-connected state.
May 19, 2026
Lenders are increasingly willing to back large-scale BESS projects in Germany that don’t have any contracted revenues, although that merchant risk is priced in to structures, an executive at Aquila Clean Energy EMEA said.
Premium
May 11, 2026
The US clean energy manufacturing industry is starting to undergo a wholesale restructuring and recapitalisation as companies look to reduce their exposure to numerous risks, including FEOC. 
Premium
May 7, 2026
What are the system needs that LDES is going to solve, and what technologies are most appropriate for those applications?