UK legislation to lift barriers on 50MW+ battery storage projects goes into effect

November 16, 2020
LinkedIn
Twitter
Reddit
Facebook
Email
Battery projects built to date in the UK have been sized at below 50MW to meet planning rules such as the 40MW Glassenbury project pictured. Image: Low Carbon.

Planning law in the UK allowing energy storage projects over 50MW has officially changed, allowing much bigger projects to come online without going through the national planning process.

In July, ministers passed secondary legislation that will allow battery storage to bypass the Nationally Significant Infrastructure Project (NSIP) process in Britain. This means storage projects above 50MW in England and 350MW in Wales to proceed without approval through the national planning regime.

The change to the Infrastructure Planning (Electricity Storage Facilities) Order 2020 has now officially passed into law, as it was made on 4 November and is set to come into force on 2 December.

Welcoming the news, Madeleine Greenhalgh, policy lead at not-for-profit energy expert group Regen wrote on LinkedIn: “The legislation which takes storage out of the national planning regime (NSIP for those in the know) has now been made into law! So from 2nd December, storage over 50MW will go through the local planning regime.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“A great success for the industry and something the ESN (Electricity Storage Network) has been pushing for some years. Thanks to those at (UK government’s Department for Energy, Industry and Industrial Strategy) BEIS who’ve put in a lot of effort to make this happen!”

The changes to the battery legislature were first announced in October 2019 when BEIS revealed that it would amend the planning legislation as a result of the responses to a consultation in January of that year.

There is currently more than 13.5GW of battery storage projects in the pipeline, according to Solar Media Market Research’s UK Battery Storage Project Database Report. There is 1.3GW ready to build, 5.7GW with planning permission and a further 6.5GW proposed.

This story first appeared on our UK solar site, Solar Power Portal.

Read Next

November 26, 2025
Mayor of Greater Manchester Andy Burnham marked the commencement of construction at Highview’s 300MWh liquid air energy storage facility.
Premium
November 25, 2025
Energy-Storage.news Premium speaks with Sky Stanfield, a member of IREC’s regulatory team and partner at law firm Shute, Mihaly & Weinberger, LLP, about the PUC’s decision and how IREC was involved.
Premium
November 24, 2025
The low prices and strict operational requirements in Italy’s recent MACSE auction for BESS have brought asset management and operational execution into the spotlight.
November 21, 2025
In a major week for European BESS deal-making, project acquisition and financing deals have been done in the Poland, Germany, Finland, the UK and Romania for grid-scale projects totalling well over 1GW of capacity.
November 14, 2025
BESS and flexible generation provider Statera Energy has secured £235 million (US$309 million) in debt financing for its 680MW/1,360MWh Carrington BESS project in Manchester, UK.