The Energy Storage Report 2024

Now available to download, covering deployments, technology, policy and finance in the energy storage market
Premium

UK BESS developer questions 2-hour duration’s suitability for net zero

LinkedIn
Twitter
Reddit
Facebook
Email

The commercial manager for Balance Power, one of two UK battery storage developers to have announced project approvals this week, has questioned whether the market standard 2-hour duration is enough to meet net zero goals in time.

Balance Power last week unveiled the first 30MW project in a 500MW pipeline partnership with TagEnergy, having secured planning approval for the project in Worcester earlier this year. And yesterday (17 July), developer Cambridge Power said it secured planning approval for a 100MW BESS in Bedfordshire.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The projects contribute to a staggering pipeline of BESS in the UK, totalling 71.4GW/100.9GWh, according to Solar Media Market Research’s UK Battery Storage Project Database Report, or as high as 118GW according to National Grid ESO figures cited by Balance Power’s commercial manager Nick Provost.

But Provost has questioned whether the 2-hour duration of most new BESS projects is adequate to decarbonise the grid in a report published on the company’s website.

“The key takeaway is that the commercial business models that developers are following today don’t align with or are unlikely to provide the technical needs that are needed to deliver a net zero grid,” Provost told Energy-Storage.news.

“In most cases the best internal rate of return (IRR) if you have a piece of land for BESS is to develop a 2-hour system. A classic project developed today is a 50MW/100MWh system. But if we actually reduced the power to 25MW to make it 4-hours or 12.5MW to make it 8-hours, that actually better aligns with net zero, because you still get all the megawatt-hours but you don’t need as many grid upgrades so projects connect quicker.”

“Our entire industry works in MW at the moment, which has been fine up until this point, but we need to transition to MWh as that will provide security of supply.”

Provost’s report estimates that 8-hour durations would be the optimal solution for providing a balance between sufficient power (MW) to deliver flexibility, while minimising the cost and time of connecting the required energy storage capacity (MWh) to the grid.

Energy-Storage.news then asked Provost what he thought needs to change to incentivise this, considering that most projects today still make the majority of revenues from ancillary services which reward MW power, not MWh capacity (even if those services are starting to saturate).

A relatively simple change would be to change the ‘de-rating factors’ for energy storage assets in the UK Capacity Market to better incentivise longer duration projects, he said. The de-rating factor is the percentage of the clearing tariff that assets will actually receive based on their technology. The figure is 95% for gas peaker plants, 46% for 4-hour energy storage systems, 24% for 2-hour ones, and around just 5% for solar PV, figures which aim to reflect the reliability of each technology in providing standby power.

But the overall key missing component is is a revenue forecast to determine how much an 8-hour project could make, Provost’s report added.

Building projects at 2-hours duration now and increasing the duration later is an option, by either reducing the power output or adding energy storage capacity, but both have big downsides. Halving the power means an over-spec’d transformer while adding capacity requires extra land.

“UK developers will often have secured planning based on the minimum amount of land they need because the size impacts planning costs and project risk,” he said. “Even if the land was available you’d need another planning process.”

Replacing the technology entirely to a longer duration one – if lithium-ion BESS is no longer the most cost-effective in, say, 10 years time – would also dent the commercials of a project if it was part-way through its expected lifetime.

See the full report from Balance Power here.

Read Next

April 26, 2024
ESB Networks has announced that Ireland’s electricity grid now has 1GW of energy storage available from different energy storage assets.
April 25, 2024
According to IEA and BloombergNEF, battery storage was the most invested-in energy tech, with biggest-ever growth in deployments recorded.
April 25, 2024
Energy Vault and utility NV Energy have put a 220MW/440MWh battery energy storage system (BESS) into operation in Nevada, US.
April 25, 2024
Developer Enerside Energy has sold a project combining agrivoltaics (agriPV) and a battery energy storage system (BESS) in Italy to Chint Solar.
April 24, 2024
Dublin-listed compressed air energy storage (CAES) project developer Corre Energy has hired investment bank Rothschild to explore the possibility of private investment in the firm.

Most Popular

Email Newsletter