UK battery project numbers fall under uncertain future for capacity market mechanism

By David Pratt
LinkedIn
Twitter
Reddit
Facebook
Email
Image: Anesco.

There has been a substantial drop in the levels of new battery capacity being entered into consideration for the UK’s Capacity Market (CM) mechanism, according to the prequalification results of the next auctions.

Late last week the transmission system operator National Grid confirmed the competing projects for its T-4 (2022-23) and T-1 (2019-20) auctions, which had been slated for January and February 2019. But after a landmark ruling from the European Court of Justice put the entire CM ‘in standstill’, future auctions have been indefinitely postponed.

A formal investigation will be carried out after the ECJ ruled that the European Commission should have further scrutinised how some technologies were treated, and could result in new terms being set for state aid under the scheme.

It is unclear how this will affect the proceedings heading into the next auctions, as a new prequalification process may be required to reflect any changes to the CM’s practices following the investigation.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

However, National Grid’s latest publications have shown stark changes in the make-up of projects seeking CM contracts in both auctions, with battery capacity seeking to prequalify for the T-4 auction falling by over 45% compared to last years’, for delivery 2021-22.

Just over 3.3GW of batteries entered into consideration compared to almost 6.2GW last time; 3.2GW has prequalified, down by almost a third on the 4.3GW of battery projects that made it through in the previous auction.

The fall in large-scale battery storage projects is likely attributable to the technology’s treatment in the last CM, where new de-rating factors were revealed after the prequalification process had already begun. Many projects with 30-minute discharge duration were hit with drastically reduced revenues, with the CM repositioned to award long duration batteries.

As a result, a small number of four-hour duration batteries have emerged in the T-4 this time around, with 11 CMUs offering a combined 431MW/1.7GWh capacity; in contrast, 66 prequalified one-hour batteries deliver the same GWh.

Ongoing reforms to other revenues available to battery storage are also likely to have impacted the number of new projects coming forward with National Grid’s review of ancillary services, regulator Ofgem’s targeted charging and significant code reviews, and slow-moving government regulation development hampering front of the meter batteries.

Some smaller behind the meter batteries have appeared within the demand side response CMUs, which saw just over 3GW prequalified in the T-4 and 2.5GW in the T-1.

More stark comparisons on the fall in large-scale batteries can be made from the T-1 auction, scheduled to deliver capacity in 2019-20, where less than 1GW of batteries attempted to prequalify; only 859.7MW was accepted. This is down by 59% compared to the previous year ahead auction.

In total 91GW of capacity was prequalified in the T-4 auction and 17.2GW in the T-1, with the majority of prequalified capacity going to gas and coal generation, and to a lesser extent interconnectors.

13 October 2026
London, UK
Now in its second edition, the Summit provides a dedicated platform for UK & Ireland’s BESS community to share practical insights on performance, degradation, safety, market design and optimisation strategies. As storage deployment accelerates towards 2030 targets, attendees gain the tools needed to enhance returns and operate resilient, efficient assets.

Read Next

October 1, 2026
Battery energy storage systems (BESS) are increasingly being positioned as essential infrastructure investments rather than purely financial assets, as seen in a series of strategic partnerships announced in late September that integrate storage with broader energy and digital infrastructure strategies.
October 1, 2026
Energy-Storage.news spoke with Noemí Gallardo, Commissioner at the California Energy Commission (CEC), at the US Solar & Storage Finance event in Garden Grove, California, about the growth of BESS within the state.
September 30, 2026
Three US utilities, Ameren Missouri, DTE Energy in Michigan, and Black Hills Energy in Colorado have recently submitted IRPs with highlighted BESS project additions.
September 30, 2026
IPP Northland Power has announced that its 80MW/160MWh Jurassic energy storage project in Cypress County, Alberta, CA, has achieved commercial operations.
Premium
September 29, 2026
Energy-Storage.news Premium speaks with Claire Lang-Ree, clean energy advocate at the Natural Resources Defense Council (NRDC), about PJM’s proposed capacity market reforms.