Tesla mega-battery reports are wide of mark, say developers of 350MW+ UK solar farm

LinkedIn
Twitter
Reddit
Facebook
Email
Tesla Powerpacks recently installed for a commercial and industrial (C&I) site in Manchester, England. Image: Photon Energy.

Cleve Hill Solar Park, the joint venture (JV) of Hive Energy and Wirsol intending to develop a 350MW+ solar farm on the Kent coast of England, has yet to make any decisions regarding the battery storage element of its plans, contrary to media reports.

Stories emerged in the UK's mainstream press last weekend linking battery giant Tesla to the project, suggesting that Elon Musk’s company was intending to develop the energy storage element of the facility.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

But the companies behind the project have strongly refuted those reports, stressing that no decisions – including on capacity and technology type – have been made.

“Cleve Hill Solar Park Ltd. is proposing to include battery storage technology in addition to the PV array in their Development Consent Order (DCO) application. Whilst the type and final number of batteries for the project is unknown, a range of scenarios will be presented in the application for the project.

“Battery storage technology is a key part of the government’s Industrial Strategy. The technology can be used in a number of ways in support of renewable energy generation including time shifting output and balancing frequency response. Battery storage technology will be part of the solution to help the grid shift from fossils fuels to renewable energy. By acting to smooth the supply of renewable energy to the grid, battery storage will play a key role in enabling an integrated low carbon energy supply. 

“Battery storage technology forms an intrinsic part of the proposal for the Cleve Hill Solar Park and is an exciting part of the future of renewable energy generation,” a statement issued to our sister site covering the UK PV industry, Solar Power Portal, read.

Planning documents reveal that the developers have requested permission for a battery facility up to 350MW in capacity, however SPP understands that the final development capacity will be resolved following discussions with National Grid.

Discussions around the final capacity and indeed the supplier of the battery storage facility may also centre on the desired duration, or mix of different battery durations. The government’s decision to de-rate battery storage facilities competing in the Capacity Market owing to their duration stands to drive interest in longer duration storage and new technologies, with some developers investigating the potential for flow batteries to be deployed at scale.

Reporting over the weekend by outlets including British daily newspapers The Times and The Daily Mail claiming Tesla CEO Musk was already lining up the project were slammed by some experts via social media for other innacuracies. Meanwhile in California, investor-owned utility (IOU) PG&E put forward for approval four projects which included a 182.5MW, four hour duration (730MWh) Tesla project

Read Next

June 19, 2025
IPP R.Power Renewables will launch construction on large-scale BESS projects in Romania and Poland in the second half of this year, while Electrica is procuring EPC works for its own BESS project.
June 18, 2025
Distributed energy company Scale Microgrids has closed US$275 million to support 140MW of distributed generation projects, including battery storage installations in several US states.
June 18, 2025
Home battery systems company Haven Energy and California utility Clean Energy Alliance (CEA)  have partnered to provide homeowners in the state with battery energy storage systems (BESS) at no purchase or installation cost.
June 18, 2025
Developer Ilmatar and investor Nuveen Infrastructure have put a 30MW/41MWh BESS in northern Finland into commercial operation.
June 18, 2025
The Philippines Department of Energy (DOE) officially opened its hugely anticipated fourth Green Energy Auction (GEA-4) round to registrants earlier this week.

Most Popular

Email Newsletter