Tech providers, contractors revealed at Brazil’s ‘non-wires alternative’ largest BESS project

LinkedIn
Twitter
Reddit
Facebook
Email

Further details about Brazil’s largest battery storage project to date have been revealed including its integrators and equipment providers.

The inauguration of the 30MW/60MWh system took place last year, on the networks of transmission system operator (TSO) ISO CTEEP, as reported by Energy-Storage.news in November.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

ISO CTEEP claimed it as the first large-scale battery energy storage system (BESS) on Brazil’s transmission grid. The project required a total US$27 million investment. The transmission operator is permitted by regulations to earn up to US$5 million revenues from the asset each year.

It will help increase hosting capacity to cope with expected increase in demand on a congested network enabling the TSO to defer from investing in a more expensive traditional transmission line, making this project an example of a ‘non-wires alternative’ or storage-as-a-transmission asset.  

It will also help reduce reliance on fossil fuel peaker plants, which can be among the most polluting and expensive generating units to run on the grid, despite typically having a low capacity factor through only coming into use infrequently during the year’s peak events.

The plant is sited at an ISO CTEEP substation in São Paulo.

US technology company Fractal EMS said yesterday that it worked on integrating the system, together with Brazilian energy storage solutions provider You.On, which was selected for the project through a competitive tender process.

Fractal EMS provided the energy management system (EMS) controls, SCADA and other components to system integrator You.On. Meanwhile You.On selected inverters from manufacturer Kehua, while the BESS is equipped with CATL’s liquid cooled battery storage solution.  

Fractal EMS CEO Daniel Crotzer said the Brazilian energy storage market “presents a significant growth opportunity,” claiming battery storage could “propel Brazil to 100% clean energy”.

You.On produced a short video ‘virtual 360° tour’ of the project (audio in Portuguese):

Read Next

March 13, 2024
Fluence will supply batteries for a 150MW/300MWh battery storage project for SSE Renewables at Fiddler’s Ferry, Warrington, UK.
Premium
March 12, 2024
System integrator Powin is working on a new grid-scale BESS product to compete with increasingly competitive product from China, senior VP Danny Lu told us, while also discussing its Waratah project in Australia and fire safety.
Premium
March 11, 2024
We heard from system integrator, developer and EPC delegates at the Energy Storage Summit EU in London last month about the implications of falling BESS prices.
March 7, 2024
The regulator in Germany has given the green light to transmission system operator (TSO) Amprion’s five ‘decentralised grid booster’ BESS projects, totalling 250MW.
Premium
March 1, 2024
Italy grid-scale energy storage market opportunities unlike anywhere else, but many challenges and uncertainties around the different revenue streams remain, including the upcoming MACSE capacity market auction.

Most Popular

Email Newsletter