SSE begins construction on 150MW/300MWh BESS in northern England

By George Heynes
LinkedIn
Twitter
Reddit
Facebook
Email

SSE Renewables has broken ground on its 150MW/300MWh battery energy storage system (BESS) in West Yorkshire, England, UK.

The renewable energy arm of energy supplier SSE confirmed that the project is scheduled to be completed by the end of 2024 and will be able to provide the grid with 300MWh of flexible capacity for two hour periods.

The project, which is located at the company’s former Ferrybridge coal-fired power station, is being developed in conjunction with battery technology supplier Sungrow Power Supply and construction partner OCU Services and will harness Sungrow’s ‘PowerTitan’ liquid cooled energy storage system.

Commenting on construction of the project starting, Richard Cave-Bigley, director of solar and battery at SSE Renewables, said: “We’re breaking new ground with our first battery at an existing SSE site. Ferrybridge used to be a coal site; but today we’ve evolved to building a 150MW flexible battery asset that can store the energy we need to help get to net zero.”

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Lewis Li, president of Sungrow Europe, added: “Sungrow is proud to supply our liquid cooled energy storage system, the PowerTitan, to this landmark project. We are excited for what is to come with our partnership with SSE Renewables as we work towards maximising the profitability for the project with cutting-edge products and services.”

The Ferrybridge project will become SSE Renewables’ second battery storage project in delivery with the company already constructing a 50MW project in Salisbury, Wiltshire, as reported by Solar Power Portal.

Building on this, the firm has also secured planning consent for battery storage projects at Fiddler’s Ferry in Cheshire (150MW) and Monk Fryston (320MW), Yorkshire.

This story first appeared on Solar Power Portal.

13 October 2026
London, UK
Now in its second edition, the Summit provides a dedicated platform for UK & Ireland’s BESS community to share practical insights on performance, degradation, safety, market design and optimisation strategies. As storage deployment accelerates towards 2030 targets, attendees gain the tools needed to enhance returns and operate resilient, efficient assets.

Read Next

June 2, 2026
Engineering giant Siemens will develop a reference architecture purpose-built for Nvidia AI data centres, in collaboration with Fluence and incorporating nVent-aligned design considerations.
June 2, 2026
Madiha Waseem of Fluence explores how early supplier engagement & procurement models are reshaping BESS delivery amid supply pressures.
June 1, 2026
Chinese-based OEM Sungrow and Spanish IPP Sonnedix have signed a supply agreement for 643.8MWh of Sungrow’s PowerTitan 2.0 solution.
June 1, 2026
RES Australia’s 2,400MWh Bunyip North BESS has cleared the federal environmental assessment process under Australia’s EPBC Act.
Premium
May 29, 2026
Managers of the UK’s largest BESS owner-operator Gresham House Energy Storage Fund (GRID) discussed recent investment news and future strategy this week.