SEC, Wirsol and Edify see 1.4GWh of Australian solar-plus-storage projects progress

November 22, 2024
LinkedIn
Twitter
Reddit
Facebook
Email

Victoria’s State Electricity Commission (SEC) and developers Wirsol and Edify Energy have seen a collective 1.4GWh of solar-plus-storage projects progress this week in Victoria and New South Wales, Australia.

Our colleagues at PV Tech reported on Wednesday (20 November) that the Australian federal government had approved Edify’s 250MW Muskerry Solar Power Station, which includes plans for a 200MW/800MWh 4-hour duration battery energy storage system (BESS).

On the same day, German renewable energy developer Wirsol lodged a modification application to increase the capacity of its Maryvale solar-plus-storage project in New South Wales to 230MW.

State-owned entity SEC contracted Swedish solar developer OX2 to deliver the 100% state government-owned 119MW SEC Renewable Energy Park.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Edify granted approval for 250MW Muskerry Solar Power Station

Australian renewable energy developer Edify Energy’s 250MW Muskerry solar-plus-storage project is located 30km northeast of Bendigo in Victoria.

According to project documents, the Muskerry solar plant will take approximately 12 months to construct and will have an operational lifespan of around 50 years.

Edify submitted the project to the Environment Protection and Biodiversity Conservation (EPBC) Act queue in October 2024. The EPBC queue, administrated by the federal government, aims to protect nationally threatened species and ecological communities under the act.

Tanya Plibersek, the Australian government’s minister for the environment and water, said that the Muskerry solar PV project is the 65th that she has approved.

“The renewable energy transition is real, it’s happening right now. And it’s the only plan supported by experts to deliver clean, affordable and reliable power,” Plibersek added.

Wirsol seeks modification to increase the capacity of its Maryvale project

Wirsol launched a modification application via consultancy HGH to increase the capacity of its Maryvale solar-plus-storage project in New South Wales. The project incorporates a 350MWh co-located BESS and is located around 37km east of Dubbo.

Construction is estimated to commence in early 2025, and commercial operations are scheduled to begin in late 2026.

The current proposal is to modify the development consent to increase the energy generation from the solar PV power plant and expand the battery discharge capacity without increasing the existing development footprint.

The project changes include upgrading the type of inverters used for the solar PV infrastructure and BESS. This modification would enable the latest generation of generation equipment to be used. An upgrade on the used solar PV modules is also being proposed alongside a potential change in their configuration.

OX2 to build AU$370 million state-owned solar-plus-storage site

Victoria’s SEC has contracted OX2 to deliver the AU$370 million (US$240 million) SEC Renewable Energy Park, including a 119MW solar PV plant coupled with a co-located 100MW/200MWh 2-hour BESS.

The project is being developed in the regional city of Horsham, around 300km northwest of the state capital, Melbourne.

The SEC Renewable Energy Park is expected to come online in 2027 and will primarily supply 100% renewable electricity to Victorian government schools, hospitals, and offices.

This becomes SEC’s second investment in Victoria’s renewable energy sector, the first being the Melbourne Renewable Energy Hub. This complex includes a 12.5MW solar PV plant and a co-located 1,200MW/2,400MWh BESS, which will be constructed across two phases and will cost around AU$1 billion.

Construction on the Melbourne hub started in early September 2024, with the first 444 Tesla Megapack battery components having been installed.

These stories appeared as separate items on PV Tech, our solar PV technology website. Read the originals here:

Government grants green light for Edify’s 250MW solar-plus-storage project in Victoria, Australia

Wirsol lodges application to expand solar-plus-storage site in New South Wales, Australia, to 230MW

OX2 to deliver AU$370 million state-owned solar-plus-storage site in Victoria, Australia

15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

March 31, 2026
The Michigan Public Service Commission has approved six battery energy storage system (BESS) projects totalling 1,332MW of capacity in the US state.
March 31, 2026
In this news roundup, Unigrid, Inlyte Energy, CIUDEN, and Sunamp are advancing non-lithium energy storage technologies worldwide.
Premium
March 31, 2026
Climate Energy Finance’s Tim Buckley argues that geopolitical instability exposes Australia’s oil dependency and positions the country as a safe haven for international renewable energy capital.
March 30, 2026
Chile continues to be Latin America’s hotspot for energy storage deployments, with a major new deal for Grenergy and Engie bringing a project online in the past week.
March 30, 2026
A 1.6GWh grid-forming battery energy storage system has received EPBC Act approval in Queensland, Australia.