Planning approval, grid connection date review for Recurrent Energy’s jointly developed 400MWh BESS in Cumbria, UK

By Cameron Murray
LinkedIn
Twitter
Reddit
Facebook
Email
A line drawing of the planned 400MWh BESS facility in Cumberland, UK, outlining positioning of containerised battery units and substation infrastructure.
A proposed site layout of the BESS project, showing the BESS containers on the right, connecting to the substation on the left. Image: Recurrent Energy / Windel Energy.

Cumberland Council in England, UK, has granted planning permission for a 200MW/400MWh BESS project from developers Recurrent Energy and Windel Energy which, unless a new grid connection date is agreed, won’t start construction until 2029.

The 2-hour duration Harker project is located between the villages of Todhills and West Linton on the outskirts of Carlisle, in the North West of England, and will connect to the Harker National Grid Substation via an underground 400kV cable.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

It is anticipated to start construction in Q4 2029, although transmission system operator (TSO) National Grid is currently reviewing the acceleration of its grid connection, which could mean it comes online sooner, Recurrent said.

The planning application approval follows a period of local consultation, Recurrent Energy said. This included meetings with various key stakeholders, a dedicated project website, extensive landscaping to provide robust visual and noise mitigation, extensive acoustic fencing to limit noise impact, the provision of detailed battery storage FAQs and the implementation of a 23% Biodiversity Net Gain aim.

Recurrent Energy is the project development arm of Canada-headquartered PV module and BESS manufacturer Canadian Solar, and just last week secured a revolving credit facility of £1.1 billion for its global pipeline.

Its BESS arm e-Storage is active in the UK market already, in December signing a deal with international utility and independent power producer (IPP) Engie for two separate 50MW/100MWh projects.

In other UK BESS industry news, this week also saw the first BESS units arrive on-site at a 150MW/300MWh project under construction by SSE Renewables, while last week developer NatPower announced plans for an earlier-stage 1GW BESS project in North East England.

This story first appeared on Solar Power Portal.

Read Next

Premium
January 20, 2025
The UK government has not ruled out changing grid access rights for new energy storage projects as part of its REMA reforms, a potential move that consultancy AFRY and investor Copenhagen Infrastructure Partners (CIP) discussed with Energy-Storage.news.
January 1, 2025
Solar PV and battery energy storage system (BESS) firm Canadian Solar will deliver 315MWh of BESS projects and up to 2GWp of solar modules to Sunraycer Renewables.
Premium
December 19, 2024
The UK is in the middle of a massive overhaul of its queue system for connecting projects to the grid, and BESS is one of the most oversubscribed technologies, leading to a “nervousness” for a lot of projects, law firm Freeths said.
December 4, 2024
A 300MW/600MWh battery energy storage system (BESS) developed by Ørsted will be co-located with its Hornsea 3 Offshore Wind Farm onshore substation.
December 2, 2024
Dispatch has begun construction on a 45MW/90MWh battery storage project in the Netherlands, with Macquarie among its backers.

Most Popular

Email Newsletter