Nidec starts building 40MW battery storage system for Neoen in Sweden

January 10, 2023
LinkedIn
Twitter
Reddit
Facebook
Email

France-headquartered independent power producer (IPP) Neoen has given system integrator Nidec ASI the green light to start work on a 40MW battery storage unit in Sweden, Neoen’s first in the country.

Nidec ASI will now start work on the Storen Power Reserve, a one-hour system in the municipality of Ragunda that will provide frequency containment reserve (FCR) ancillary services to transmission system operator Svenska Kraftnät.

The battery system will come into commercial operation in the first half of 2024, the companies said. Neoen will own and operate the asset.

It is Neoen’s first battery storage project in Sweden and its third renewable energy project there, after the Storbrännkullen wind and Hultsfred solar projects which are under construction and set to start construction in the second half of this year, respectively.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

It is the company’s second battery project in the Nordics after it enlisted Nidec ASI to build it a 30MW/30MWh unit in Finland in 2020.

Battery energy storage projects in Sweden have started to ramp up in the past year as the country’s pumped hydro energy storage (PHES) reaches the upper limit of its capacity to balance the grid.

Last month, developers OX2 and Ingrid Capacity started work on two battery storage projects totalling 60MW of power while the latter said in September that it was also building a 70MW unit, the largest in the country – all three for 2024 delivery dates.

Sandwiched in between those two announcements by Ingrid was news of what was claimed by project developer Alight to be the largest solar-plus-storage unit in the country, combining a 2MW battery system and an existing 12MW solar PV array. The company said in October that the new energy storage system would come online in two months’ time.

Nidec ASI is the Italy-based industrial solutions division of Japanese conglomerate Nidec Corporation and was ranked as one of the largest battery storage system integrators in the world in IHS Markit’s 2021 report.

It has recently signed big deals with lithium-ion battery gigafactory startup FREYR to build 12GWh of battery energy storage systems a year by 2030, and deploy 5.4MWh of battery systems by an unnamed company in Italy.

Neoen has been even busier in the last few weeks and months with several large project announcements in Australia.

Energy-Storage.news’ publisher Solar Media will host the eighth annual Energy Storage Summit EU in London, 22-23 February 2023. This year it is moving to a larger venue, bringing together Europe’s leading investors, policymakers, developers, utilities, energy buyers and service providers in one place. Visit the official site for more info.

Read Next

Premium
December 11, 2025
Energy-Storage.news Premium speaks with John Farrell, Co-Director of The Institute for Local Self-Reliance (ILSR), on rising utility costs and the role energy storage can play.
December 10, 2025
AFC and public-private-partnership (PPP) Cabeolica have inaugurated 13.5MW of wind power generation and 26MWh of battery storage in Cape Verde.
December 9, 2025
The 600MW/1.6GWh Melbourne Renewable Energy Hub has commenced commercial operations in Victoria, Australia.
December 5, 2025
Developer BrightNight and independent power producer (IPP) Cordelio Power have announced financial close of the 200MW/800MWh Greenwater battery energy storage system (BESS) in Washington state, US.
December 4, 2025
PJM has awarded 23 battery energy storage system (BESS) resources, totalling 2.2GW, with interconnection agreements (IAs) in its first transition cycle (TC1) of the reformed interconnection process.