An obvious hurdle for battery storage in the Capacity Market is the de-rating factors employed by market facilitator National Grid for the asset class. Image: Getty.

Battery storage submissions for forthcoming Capacity Market auctions in the UK have dwindled, with demand side response (DSR) emerging as the clean technology of choice.

Late last week the UK’s EMR Delivery Body, the entity tasked with facilitating the Capacity Market auction and qualification process, released the list of assets that have successfully pre-qualified for the T-1, T-3 and T-4 auctions taking place early next year.

But despite strong interest from battery storage assets in previous auctions, interest in next year’s auctions would appear to be dwindling, perhaps as a direct result of de-rating factors which have significantly dampened the business case for batteries within the mechanism.

Of the 4.6GW of energy capacity to have pre-qualified for the T-1 auction – procuring capacity for the 2020-21 winter period – just 54W of battery storage assets have been successful. This is spread between 10 separate battery projects.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

In the T-3 auction, which is to procure capacity for the 2022-23 winter period, around 501MW of battery storage capacity has come forward, less than 1% of the 58.4GW of capacity pre-qualified for that auction.

The T-4 auction for 2021-22 held in November last year brought forward around 3.3GW of pre-qualifications, however that had fallen by around 45% compared to the T-4 auction pre-qualification results the year before.

This number has fallen again, but more dramatically. This year’s T-4 auction for the 2023/24 winter period has seen just 371MW of battery storage assets come forward, representing just 0.5% of the 62GW of capacity to have pre-qualified.

While there is a positive development in that a prospective co-located solar-plus-storage project, located in North Anglesey, Wales, has been pre-qualified for the T-3 and T-4 auctions – the first such time a renewables generator has been pre-qualified since that asset class was waved into the Capacity Market earlier this year – a lack of battery storage projects coming forward for CM contracts will be met with interest by industry stakeholders.

An obvious hurdle for battery storage in the Capacity Market is the de-rating factors employed by market facilitator National Grid for the asset class, designed to better represent the contribution limited-duration battery technologies can have at times of system stress.

While incentivising longer-duration technologies, the de-rating factors have been described as “fatally onerous” for shorter-term batteries by those in the UK market.

Read Next

December 5, 2025
Developer BrightNight and independent power producer (IPP) Cordelio Power have announced financial close of the 200MW/800MWh Greenwater battery energy storage system (BESS) in Washington state, US.
December 4, 2025
Jason Beer of Fluence Australia, discusses some energy trends in Australia that are set to influence the development of the storage market.
December 2, 2025
Manoa Energy and HD Renewable Energy Japan have begun commercial operation of a 50MW/104MWh battery storage project in Hokkaido, Japan.
December 1, 2025
European BESS news from project owners Premier Energy Group, Verbund, Eco Stor, Ingrid Capacity, Ric Energy, Ganfeng Lithium, EP Group, RWE and Giga Storage, securing acquisitions, financings and route-to-market (RTM) deals for multiple gigawatts of capacity this past week.
November 28, 2025
The Australian government has officially opened CIS Tender 8, targeting 16GWh of energy storage capacity across the NEM.