KORE Power has edged closer to the launch of its Mark 1 battery cells after the company landed a handful of product safety certifications.

Earlier this week the manufacturer confirmed that it had successfully achieved the UN 38.3, UL 1973 and IEC 62619 certifications, placing KORE on track to fulfill its first customer orders later this quarter.

Testing of the Mark 1 module and rack will now begin later this month in order for the units to conform with UL 1973, UL 1998, UL 991, UN 38.3 and IEC 62619 tests, all of which relate to the use of batteries in stationary energy storage, battery management software and the actual transportation of lithium-ion batteries.

KORE also confirmed it was now in the final stages of selecting an accredited certification body to complete testing of its Mark 1 product in accordance with UL 9540A safety certification – which relates to thermal runaway fire precautions.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

But in the meantime the company intends to begin shipping modules to regions that do not specifically require the UL9540A certification, including the US, Europe, India and Australia.

KORE now expects to ramp up Mark 1 production and realise installations in utility-scale energy storage systems later this year.

Lindsay Gorrill, chief executive of Idaho-based KORE, said that completing the first round of product certification testing represented a “major growth milestone” for the firm, stating that the certification would allow it to prove the safety and efficacy of its batteries and begin to fulfil orders.

In September last year KORE set its sights high, aiming to have 6GWh of annual production capacity of its high-power nickel manganese cobalt (NMC) battery cells up and running by the end of Q1 2020.

Read Next

Sponsored
November 26, 2025
As Australia accelerates its transition toward renewables, demand for reliable & sustainable energy storage solutions has never been higher.  
November 24, 2025
Developer Akaysha Energy has confirmed that the 850MW Waratah Super Battery will undergo a planned balance of plant shutdown from 20 November to 2 December 2025.
Premium
November 21, 2025
The Community Development and Infrastructure Department at Santa Cruz County has become the latest California jurisdiction to publish a draft zoning ordinance regulating the deployment of battery energy storage systems. 
November 21, 2025
In a major week for European BESS deal-making, project acquisition and financing deals have been done in the Poland, Germany, Finland, the UK and Romania for grid-scale projects totalling well over 1GW of capacity.
November 13, 2025
The three-year rolling partnership, whereby CATL will supply HyperStrong with cells and system products, could be updated annually.