‘Interconnection rules for energy storage are a work in progress’, even in the US’ leading states

LinkedIn
Twitter
Reddit
Facebook
Email
“As the interconnection of energy storage evolves in the coming years, best practices for how best to analyse their grid impacts will continue to emerge.” Image: Sonnen.

Even the US states leading in energy storage market development still have work to do when it comes to adopting the best and lowest-cost grid interconnection procedures, an expert in regulatory affairs at the Interstate Renewable Energy Council (IREC), has said.

In an exclusive blog published this week on Energy-Storage.news, Sara Baldwin, the national group’s VP for regulatory affairs, wrote that while “interconnection procedures are the rules of the road for the grid,” at this stage, such rules vary hugely state by state.

“Without common rules and predictable processes, gridlock and costly projects can result. Alternatively, the adoption of statewide interconnection standards (i.e., rules that apply to all regulated utilities) that reflect well-vetted best practices can provide greater consistency across utilities and help streamline the grid connection process for all involved stakeholders,” Sara Baldwin wrote.

IREC produced its latest Model Interconnection Procedures in September this year, applicable nationally and designed to “reflect the latest evolution in best practices to facilitate higher penetrations of distributed energy resources (DERs) on the grid,” including wind, solar, electric vehicles and, of course, energy storage.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The 2019 edition provides a “necessary update” to the guide first published in 2005 and subsequently updated in 2009 and 2013, Baldwin said at the time it was released, aimed at informing stakeholders including utility regulators, industry professionals and policymakers.

While the new document includes an initial framework for the interconnection of energy storage systems, as outlined in the IREC expert’s blog, they remain very much a work in progress and “do not yet resolve every question around energy storage.”

“For example, they (the procedures) do not address how to screen those energy storage systems that may have some ‘inadvertent export’ for a very short duration in response to sudden customer load fluctuations,” Baldwin wrote.

“But as the interconnection of energy storage evolves in the coming years, best practices for how best to analyse their grid impacts will continue to emerge.”

Read Sara Baldwin of IREC’s blog for Energy-Storage.news, “Encouraging signs: interconnection rules in the age of distributed energy storage”, here.

15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

July 10, 2026
Peak Energy, ESS Tech Inc, and Unigrid have made recent announcements advancing sodium-ion energy storage technology in the US and Europe.
July 9, 2026
Independent power producer (IPP) Opdenergy has closed a US$227 million financing for its operating renewable energy portfolio in Chile. 
July 9, 2026
Long-duration energy storage (LDES) development and investment company Frontier Power USA (FPUSA) has exercised its exclusive Selection Right with respect to four BESS projects from clean energy platform Stella Energy Solutions.
July 9, 2026
AI data centre battery storage announcements on both sides of the Atlantic explore the tapping of grid-balancing revenues and distributed computing.
July 8, 2026
Developer New Leaf Energy withdrew its application for a battery energy storage system (BESS) in Santa Cruz County, California, US, choosing to seek approval through the California Energy Commission (CEC).