Major US utility Florida Power & Light Company (FPL) is planning to build the world’s largest battery energy storage system adjacent to an existing solar power plant, with plans to roll out multiple other storage systems across the state.

With the key proposed battery standing at 409MW capacity, the Florida energy company claims it will be four times larger than the largest battery currently operating worldwide. Furthermore, the system will help reduce fossil fuel usage and thereby accelerate the decommissioning of two neighbouring, 1970s-era natural gas power units.

The FPL Manatee Energy Storage Center will be powered by an existing PV plant in Parrish, Manatee County, and capable of distributing 900MWh of electricity. It will start serving customers in 2021, with the batteries being used particularly during peak demand periods, thereby reducing the requirement for electricity from other power plants. It will be able to provide energy the equivalent of 329,000 homes for a period of two hours, saving FPL customers more than US$100 million in the process.

Eric Silagy, president and CEO of FPL, said: “This is a monumental milestone in realizing the full benefits of solar power and yet another example of how FPL is working hard to position Florida as the global gold standard for clean energy.”

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The company has 18 solar power plants currently in operation and four more entering construction, but it is no stranger to solar-plus-storage, having opened the largest plant combining solar and storage at Babcock Ranch in Charlotte County in 2018, and the company is now also planning smaller battery installations and solar plants across the state. This, while carrying out efficiency upgrades to existing combustion turbines at other power plants, will help to replace 1,638MW of traditional generating capacity.

“Even as we aggressively execute on our plan to install 30 million solar panels by 2030, we never lose sight of finding innovative ways to bring our customers the benefits of solar energy, even when the sun’s not shining,” added Silagy. “Replacing a large, ageing fossil fuel plant with a mega battery that’s adjacent to a large solar plant is another world-first accomplishment.”

FPL’s two-decade-long modernisation programme has tended to involve replacing oil-based power plants with US-produced natural gas units. However, it is FPL’s increased knowledge of how to optimise solar and batteries as well as the new technologies’ rapidly declining costs, that is allowing FPL to take on these alternative technologies simultaneously.

“The way we generate, store, transport and use electricity is being reinvented. New technology, like large-scale battery storage, is a critical step on the path to a cleaner, cheaper and more efficient energy future. Achieving this outcome is critical to the well-being of our economy, our communities and our planet,” said Temperince Morgan, executive director of the Florida Chapter of The Nature Conservancy.

FPL, which serves more than 10 million people, will also soon shut down its only remaining coal plant in Florida by the end of this year.

11 November 2025
San Diego, USA
The 2024 Summit included innovative new features including a ‘Crash Course in Battery Asset Management’, Ask-Me-Anything formats and debate-style sessions. You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

October 9, 2025
H.I.G. Capital-backed energy platform, Greenflash Infrastructure, has closed a hybrid tax capital and debt financing for Project Soho, a 400MW/800MWh standalone battery storage project in Brazoria County, Texas.
October 9, 2025
GoldenPeaks Capital (GPC) and Huawei Polska have signed a Memorandum of Understanding (MoU) on a Battery Energy Storage System (BESS) cooperation focusing on 500MWh grid-forming BESS in Europe.
October 9, 2025
Battery energy storage revenues in Australia’s National Electricity Market (NEM) fell 61% in September 2025 to AU$85,000/MW (US$56,712/MW) as price volatility eased across the grid, according to new research from Modo Energy.
Premium
October 8, 2025
Utah Associated Municipal Power Systems (UAMPS) has negotiated the terms of a solar and BESS power purchase agreement (PPA) with Boston, Massachusetts-based developer Longroad Energy.
October 8, 2025
US utility Xcel Energy has proposed to build out a 200MW battery storage network across Minnesota, US.

Most Popular

Email Newsletter