Construction imminent on major solar-wind-storage hybrid plant in Queensland

LinkedIn
Twitter
Reddit
Facebook
Email
The park includes 43MW of wind, 15MW of solar on single-axis trackers, and two lithium-ion batteries. Credit: Windlab

Construction on Australia’s first utility-scale wind, solar and energy storage hybrid project to be connected to the national grid is about to start near Hughenden in northwest Queensland.

Australian developer Windlab put out a similar release in October, but construction on the roughly 60MW plant is now due to start today. The project is owned by Windlab and its equity partner Eurus Energy Holding Corporation of Japan.

The innovative AU$160 million Kennedy Park Energy will take around 12 months to construct and is expected to be completed and start feeding clean energy into the network by late 2018, according to Windlab’s executive chairman and chief executive Roger Price.

He added: “This is an industry first that will produce and feed clean renewable energy into the grid with much greater consistency and reliability from a combination of solar, wind and battery storage. It’s also an important and valuable demonstration of how renewable energy can be used to cost effectively meet most network demand for power – day and night. We believe that this style of hybrid configuration will be increasingly used, particularly in remote locations and emerging markets, as the world transitions to a clean energy future. We are excited about the opportunities that the expertise gained from this pioneering project will present as we seek to replicate it across selected locations in Australia and Southern Africa.”

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The park includes 43MW of wind, 15MW of solar on single-axis trackers, and two lithium-ion batteries. This includes 56,000 solar panels and twelve Vestas V136, 3.6MW wind turbines.

Kennedy Energy Park secured finance from the Clean Energy Finance Corporation (CEFC) and the Australian Renewable Energy Agency (ARENA), as part of ARENA’s Advancing Renewables Programme.

Utility CS Energy will purchase the energy from Kennedy Energy Park under a 10-year power purchase agreement.

In a statement, Windlab said: “Queensland’s typical daily electricity demand increases during late afternoon and evening and is well matched to the timing to the state’s wind energy profiles. This means Queensland wind farms will produce most of their electricity at these times, which coincide with high network demand. Combining wind with the large amounts of solar generation expected to be added to the Queensland grid, will allow a higher penetration of renewable energy at lower costs while reducing the need for storage and other peaking capacity across the network.”

The next stage of the project named ‘Big Kennedy’ is set to provide up to 1,200MW of wind energy as well.

Read Next

May 12, 2026
Energy storage owner-operator BW ESS has submitted a 700MW battery energy storage system (BESS) to Australia’s Environment Protection and Biodiversity Conservation (EPBC) Act for environmental assessment.
Premium
May 12, 2026
In this interview with ESN Premium, Keith Lovegrove of ITP Thermal warns that Australia’s energy storage sector risks over-reliance on lithium-ion batteries.
May 11, 2026
Energy storage developer and system integrator Energy Vault has released its Q1 2026 financial results, showing expansion in its project portfolio, AI infrastructure activities, and operations in Australia and Japan.
May 11, 2026
Developer Alternate Path has secured federal environmental approval for its 500MW/2,000MWh Murchs Corner battery energy storage system (BESS) in Victoria, Australia.
May 8, 2026
Independent power producer (IPP) Innergex and system integrator Prevalon Energy have energised the San Andrés II battery energy storage system (BESS) in Chile.