NEC Energy Solutions to supply SoCal Edison with first grid energy storage system under procurement

November 4, 2016
LinkedIn
Twitter
Reddit
Facebook
Email

The NEC ES GSS® grid storage solution is the first grid energy storage pilot system under a pre-approved energy storage procurement program initially conceived of and announced by SCE last year. Source: NEC Energy Solutions
Battery manufacturer and developer NEC Energy Solutions is to supply Southern California Edison (SCE) with its first grid energy storage pilot system under a procurement programme established last year.

The NEC ES GSS grid storage solution is a ‘plug-and-play’ procurement strategy being used by the Californian utility to pilot energy storage as a grid stabilising solution. It allows SCE to employ energy storage with a variety of features and configurations on-demand and could be installed almost anywhere across the state to support SCE pilot programmes.

The first storage system delivered under the procurement programme will include 3.4MWh of containerised lithium-ion batteries, a 3MW power conversion system and NEC Energy Solution’s software controls.

The energy storage system will be installed to prevent conventional grid upgrades that are becoming increasingly challenging, particularly in dense urban environments such as those found in SCE service territory. NEC Energy will also provide service and maintenance offerings to the utility for the upkeep of the energy storage system.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“Commercialisation of energy storage in a way that allows quick and easy procurement has always been a goal of ours,” said Bud Collins, CEO, NEC Energy Solutions, in a statement. “We worked extensively with SCE on this innovative programme to make energy storage transactional while ensuring safety, reliability, and cost-effectiveness of the technology. Programmes like this will make energy storage – a fast, flexible, clean, and dispatchable resource – an integral part of the grid.”

Recently, SCE and GE announced that they plan to install the world’s first battery storage and gas turbine hybrid. SCE is one of California’s three investor owned utilities that make up around 75% of the state’s electricity supply andare bound by AB2514, the mandate that orders the utilities to put 1.3GW of energy storage on the grid by 2020.

Read Next

Premium
November 26, 2025
Energy-Storage.news Premium speaks with Michael Kirschner, Managing Director, US, for Habitat Energy, about optimising BESS projects in ERCOT.
November 25, 2025
Texas-based IPP Vistra Energy has informed the California Energy Commission (CEC) that it will not be advancing its 600MW Morro Bay battery energy storage system (BESS).
Premium
November 25, 2025
Energy-Storage.news Premium speaks with Sky Stanfield, a member of IREC’s regulatory team and partner at law firm Shute, Mihaly & Weinberger, LLP, about the PUC’s decision and how IREC was involved.
November 25, 2025
San Diego-based home battery storage company NeoVolta has entered into agreements for a US$13 million private placement financing anchored by Infinite Grid Capital (IGC).
November 24, 2025
Developer Akaysha Energy has confirmed that the 850MW Waratah Super Battery will undergo a planned balance of plant shutdown from 20 November to 2 December 2025.