India’s SECI consults industry on 160MW solar-wind-storage hybrid plan

January 24, 2018
LinkedIn
Twitter
Reddit
Facebook
Email
A wind-plus-energy storage installation in the Netherlands. Image: Alfen

Solar Energy Corporation of India (SECI) has reached out to industry to establish how much interest there is in providing EPC services for a 160MW solar-wind hybrid project coupled with energy stroage in the state of Andhra Pradesh.

Shaurya Bajaj, analyst at consultancy firm Bridge to India, told PV Tech that SECI will own the pilot project and it will be financed with help the World Bank, IBRD and Clean Tech Fund to the tune of US$200 million.

This project, tentatively located in Ramgiri district, would certainly be the largest and amongst the first of its kind built in India. However a smaller pilot project is also being planned in Kerala, as reported by our sister site PV Tech back in December.

SECI clarified that the aim of its notice was only to learn about the market scenario for the solar and wind hybrid project, along with the suitable deployment of energy storage solutions. It also wants to gain an idea of eligible interested national and international bidders, their financial and technical capacities, relevant experience in the sector and their capacity and interest to participate in the pilot. This is not part of the initial selection process or contract award.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

Bajaj described SECI’s procurement notice as innovative – adding: “Since the draft wind-solar hybrid policy was announced in 2016 not much has happened on ground, same is the case for utility-scale storage. It seems that MNRE wants to build a pilot project to encourage the adoption of new RE technology in the country.”

Shared infrastructure for the project will be provided by New and Renewable Energy Development Corporation of Andhra Pradesh (NREDCAP) while transmission evacuation facilities will be provided by Andhra Pradesh Transmission Company Limited (AP Transco).

Power generated from the project will be sold by SECI to the potential off-takers including Andhra Pradesh distribution companies (Discoms) via a long-term power purchase agreement (PPA).

In August 2016, Andhra Pradesh has released a draft document outlining its plans for 3GW of wind and solar hybrid projects by 2019/20, which followed the Ministry of New and Renewable Energy’s (MNRE) release a draft of a national Wind-Solar Hybrid Policy targeting 10GW by 2022.

Read Next

November 6, 2025
IPPs BrightNight and Cordelio Power have reached financial close on the 300MWac solar PV, 300MW/1,200MWh battery energy storage system (BESS) Pioneer Clean Energy Centre in Yuma, Arizona, US.
November 5, 2025
India’s energy storage industry is at a turning point as developers, financiers, and policymakers work to define viable business models for the next wave of large-scale battery projects. 
November 5, 2025
Utility Osaka Gas and developer Sonnedix are installing what is claimed to be the largest battery storage facility co-located with renewable energy generation in Japan so far.
Premium
November 5, 2025
ESN Premium speaks with Neha Sinha of Wärtsilä Energy Storage, about DC-coupled solar-battery hybrids in Australia.
November 4, 2025
Partnerships will determine whether India can emerge as a global hub for battery manufacturing and energy storage.

Most Popular

Email Newsletter