Georgia Power announces 2025 RFP for 500MW of BESS

September 26, 2025
LinkedIn
Twitter
Reddit
Facebook
Email

Utility Georgia Power has announced the open comment period for its 2025 Request for Proposals (RFP) for battery energy storage system (BESS) resources. 

This RFP, approved by the Georgia Public Service Commission (PSC) as part of the company’s 2022 Integrated Resource Plan (IRP), provides a competitive solicitation for Georgia Power to procure 500MW of BESS.

The company aims to have the procured resources online by the end of 2031 at the latest.

The RFP, managed by independent evaluator Ascend Analytics, will invite proposals for standalone BESS with grid charging capability, as well as BESS integrated with renewable resources (new or existing) and grid charging capability.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The procurement target capacity is 500MW, with a required storage discharge duration of at least two hours.

In August, Georgia Power required certification from the Georgia PSC for 9,900MW of new generation resources, including more than 3GW of battery storage that the utility would own.

About 8,000MW of the requested resources were selected from an “all-source” RFP approved in Georgia Power’s 2022 Integrated Resource Plan (IRP).

Over the past year, the All-Source RFP involved collaboration between the company, Georgia PSC staff, and an independent evaluator.

The primary objective was to identify the most cost-effective and efficient proposals for dispatchable generation and storage resources, ensuring that construction schedules meet the projected winter capacity requirements from 2029 to 2031.

In May, the company began constructing 765MW of new BESS across the state. This capacity was increased from 500MW, which the Georgia PSC unanimously approved in 2024.

As reported by our colleagues at PV Tech, the Georgia PSC approved Georgia Power’s 2025 IRP in July of this year.

The utility initially proposed the 2025 IRP in January, building on a 2023 version of the document. Georgia Power anticipates an 8.5GW increase in electrical load in the state by 2030, which is over 2.6GW higher than the 2023 forecasts. The approved 2025 IRP outlines Georgia Power’s strategies to address this rising demand.

Participants interested in the 2025 RFP must register through the Ascend Analytics Power Procurement platform. They will then receive an invitation to attend the RFP Bidder’s Conference on 29 September, either in person or virtually.

Georgia Power says participants should visit the independent evaluator website for additional RFP and Solicitation Schedule details.

24 February 2026
InterContinental London - The O2, London, UK
This isn’t just another summit – it’s our biggest and most exhilarating Summit yet! Picture this: immersive workshop spaces where ideas come to life, dedicated industry working groups igniting innovation, live podcasts sparking lively discussions, hard-hitting keynotes that will leave you inspired, and an abundance of networking opportunities that will take your connections to new heights!
24 March 2026
Dallas, Texas
The Energy Storage Summit USA is the only place where you are guaranteed to meet all the most important investors, developers, IPPs, RTOs and ISOs, policymakers, utilities, energy buyers, service providers, consultancies and technology providers in one room, to ensure that your deals get done as efficiently as possible. Book your ticket today to join us in 2026!
9 June 2026
Stuttgart, Germany
Held alongside The Battery Show Europe, Energy Storage Summit provides a focused platform to understand the policies, revenue models and deployment conditions shaping Germany’s utility-scale storage boom. With contributions from TSOs, banks, developers and optimisers, the Summit explores regulation, merchant strategies, financing, grid tariffs and project delivery in a market forecast to integrate 24GW of storage by 2037.
15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

January 30, 2026
US battery energy storage system (BESS) developer-operator Jupiter Power has closed a US$500 million senior secured green revolving loan and letter of credit facility to support the advancement of its project pipeline across the US.
January 30, 2026
Redwood Energy announced the final closing of its Series E financing round, bringing the total raise to US$425 million.
Premium
January 29, 2026
“We see energy storage as an opportunity for (data centres) to reduce their impact on the grid”, said Patrick Hughes, Senior VP of Operations and Strategy at NEMA.
January 29, 2026
Long-duration energy storage (LDES) developer-operator Hydrostor has announced a strategic technology and equity agreement with energy infrastructure equipment manufacturer Baker Hughes.
January 28, 2026
US sodium-ion (Na-ion) battery technology company Unigrid has begun international shipments of its proprietary sodium cobalt oxide (NCO) cathode cells at commercial volume.