FRV and AGL advance 2,200MWh of grid-forming battery energy storage in Australia

December 3, 2025
LinkedIn
Twitter
Reddit
Facebook
Email

Two battery energy storage systems (BESS) developments from FRV Australia and AGL Energy, totalling 2,200MWh, have reached major milestones in Australia.

FRV Australia achieves grid connection for 200MWh Terang grid-forming BESS

FRV Australia connected its first battery energy storage system project to the grid, marking the energisation of the 100MW/200MWh Terang BESS in southwestern Victoria.

The project represents a major milestone for the company’s expansion into Australia’s energy storage sector and contributes to grid stabilisation efforts in the National Electricity Market (NEM).

The facility utilises intelligent algorithms to optimise performance while reducing demand peaks and supporting the transition toward a more sustainable electricity grid. Construction of the Terang BESS has reached near completion, with the project now entering the commissioning phase following successful grid connection.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Canadian Solar subsidiary e-STORAGE supplied the battery storage system for the Terang BESS, which marks FRV Australia’s first standalone storage project. The project will also benefit from Fluence’s Mosaic software optimisation for the 200MWh grid-forming BESS, enhancing operational efficiency and grid support capabilities.

The facility’s grid-forming capabilities enable it to provide essential system services while supporting grid stability during periods of high renewable energy penetration.

AGL commences construction on 500MW Tomago Battery Project

Meanwhile, AGL has commenced construction on its 500MW Tomago Battery Project in New South Wales following a groundbreaking ceremony attended by AGL CEO and managing director Damien Nicks, and chief operations and construction officer Matthew Currie.

Federal minister for climate change and energy Chris Bowen and the New South Wales minister for the Hunter Yasmin Catley also attended the ceremony alongside media representatives, local council members, community stakeholders and project partners.

The AU$800 million (US$516 million) grid-scale battery storage system, targeting operations in the second half of 2027, represents one of Australia’s largest BESS developments with 2,000MWh capacity designed to strengthen the state’s energy infrastructure.

AGL plans to begin operations at the Tomago Battery Project in the second half of 2027.

Fluence secured its biggest global contract for the 2,000MWh grid-forming battery energy storage system. Fluence said it would supply its Gridstack Pro for the utility-scale energy storage project.

Fluence launched the Gridstack series in 2020 and Gridstack Pro followed in 2023, which Fluence said at the time was aimed at the largest and most complicated projects its customers are undertaking.

Fluence has been contracted to construct the project and provide ongoing service and maintenance.

AGL previously secured regulatory approval for the 2,000MWh BESS development in November 2024, clearing the path for construction to commence.

The total construction cost of this grid-forming battery storage project is estimated to be approximately AU$800 million. Much like the Terang BESS, the Tomago Battery project will connect to the NEM.

AGL also has a target to add 12GW of renewables and firming to its portfolio by 2035.

17 March 2026
Sydney, Australia
As we move into 2026, Australia is seeing real movement in emerging as a global ‘green’ superpower, with energy storage at the heart of this. This Summit will explore in-depth the ‘exponential growth of a unique market’, providing a meeting place for investors and developers’ appetite to do business. The second edition will shine a greater spotlight on behind-the-meter developments, with the distribution network being responsible for a large capacity of total energy storage in Australia. Understanding connection issues, the urgency of transitioning to net zero, optimal financial structures, and the industry developments in 2026 and beyond.
6 October 2026
Warsaw, Poland
The Energy Storage Summit Central Eastern Europe is set to return in September 2025 for its third edition, focusing on regional markets and the unique opportunities they present. This event will bring together key stakeholders from across the region to explore the latest trends in energy storage, with a focus on the increasing integration of energy storage into regional grids, evolving government policies, and the growing need for energy security.

Read Next

January 9, 2026
Jointly owned by Masdar and Igneo Infrastructure Partners, independent power producer (IPP) Terra-Gen’s Lockhart CL I and II battery energy storage system (BESS) projects have reached commercial operations in San Bernardino County, California, US.
Premium
January 9, 2026
Javier Savolainen of Wärtsilä explains how Australia’s battery storage and pumped hydro fleet have been impacted by the current heatwave.
January 9, 2026
Yanara has appointed Gamuda Australia as the project delivery partner for the early contractor involvement (ECI) phase of the Mortlake Energy Hub in Victoria.
January 8, 2026
News from Canada, as NB Power issues a request for expressions of interest for 50MW of energy storage, while Boralex commissions its energy storage project with Walpole Island First Nation.
January 8, 2026
H.I.G. Capital-backed energy platform, Greenflash Infrastructure, has Safe Harboured more than 10GWh of lithium-ion (Li-ion) energy storage capacity.