Enlight commissions solar-plus-storage projects in Israel as market liberalises

LinkedIn
Twitter
Reddit
Facebook
Email

Renewable energy firm Enlight has commissioned two solar-plus-storage projects in Israel in the last few weeks, totalling 71MWh of energy storage capacity.

Enlight Renewable Energy has put the 17MW PV, 31MWh Arad Valley 1 project into commercial operation, it announced this week (11 September).

This comes a few weeks after it announced the commercial operation of another solar-plus-storage project, Sde Nitzan, which combines 23MW of solar PV and 40MWh of energy storage. Enlight claimed at the time that it was Israel’s first combined solar and storage project.

The two are part of a cluster of solar-plus-storage projects in Israel that Enlight is developing totalling 248MW of solar PV and 474MWh energy storage capacity. The remaining projects are under construction and are expected to come online between now and end of H1 2024.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

Energy generated by the projects will be sold through the firm’s integrated power supply model, under the company’s recently signed corporate power purchase agreements (PPAs) as well as a partnership with utility Electra Power to supply residential and small commercial customers.

The electricity market in Israel will be fully liberalised in January 2024, with the introduction of competition to its wholesale and retail energy markets.

Enlight is also active in Europe, building up a substantial operational PV portfolio in Hungary, as well as the US where it has been signing long-term PPAs with utilities in Arizona for a large solar-plus-storage project which is expected to come online in 2025.

Read Next

August 29, 2025
The Australian government has opened two CIS tenders in Western Australia, targeting 2.4GWh of energy storage and 1.6GW of renewables.
August 27, 2025
“Battery energy storage systems (BESS) typically change ownership between two and four times during their 40-year lifecycle,” John Sheehy, CEO of Pottinger, said on day two of the Battery Asset Management Summit Australia 2025 this morning.
August 26, 2025
After an initial rush to deploy that gave CAISO and ERCOT the lead in US BESS adoption, both markets are focused on capacity and availability, writes Amit Mathrani of Rabobank Americas.
August 26, 2025
BESS developer Pacific Green Technologies has secured a AU$77 million (US$49.9 million) debt facility for projects in Australia.
August 26, 2025
“We’re expecting the results of the Capacity Investment Scheme (CIS) Tender 3 in the coming weeks,” Thimo Mueller, general manager, commercial at ASL, said in the opening keynote of the Battery Asset Management Summit Australia 2025 this morning.

Most Popular

Email Newsletter