Engie Chile starts commercial operation of 139MW/638MWh BESS in Antofagasta

March 20, 2024
LinkedIn
Twitter
Reddit
Facebook
Email
Engie Chile's BESS Coya project in Antofagasta, Chile with a 5-hour duration
The BESS Coya project in Antofagasta is Engie’s largest BESS plant in Latin America. Image: Engie Chile.

Utility and independent power producer (IPP) Engie has started commercial operations of a 139MW/638MWh battery energy storage system (BESS) in the northern region of Antofagasta, Chile.

The BESS Coya project, which uses lithium-ion (Li-ion) batteries and has a 5-hour duration, has been paired with the 180MW solar PV plant of the same name. China-based solar PV inverter and energy storage system manufacturer Sungrow provided the equipment for the BESS Coya project. It is made up of 232 containers.

This is Engie Chile’s largest BESS project in the country, and the company is currently building two other BESS projects in Chile that will be co-located with solar PV plants. Last month the utility started construction of a 5-hour duration battery storage system with a power output of 48MW and a capacity of 264MWh to be paired with an 88MW plant in Antofagasta.

Also in Antofagasta, the company is adding a 68MW/418MWh BESS to the nearby Tamaya solar project, pictured above, with Sungrow as the provider for the batteries.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“The lack of optimisation from renewables generated in the north of Chile has always been one of our concerns. For this reason, we decided to include a storage system during the development of the Coya solar PV plant, with the goal to inject energy to the system during night, when it is most needed,” said Rosaline Corinthien, CEO at Engie Chile.

Most large solar PV projects in Chile are adding energy storage to mitigate the huge levels of curtailment seen in the last few years, while standalone energy storage projects are being deployed to capitalise on capacity market and broader energy trading opportunities (made possible by a new bill passed in late 2022).

Furthermore, earlier this year the Chilean government formed an entity to keep a majority stake in domestic lithium production with one of the two private companies that mine it, while also setting aside land for 13GWh of downstream energy storage projects.

Returning for the third edition in Santiago, Chile, the Energy Storage Summit Latin America will explore opportunities in countries such as Chile, Peru, Colombia, Argentina, Brazil and Mexico. Join Solar Media on October 15-16 to meet with investors, policy makers, developers, utilities, network operators, technology providers, EPCs, consultants, law firms and more to make sure you are a part of the rapidly evolving storage landscape in Latin America. More information, including how to attend, can be read here.

27 October 2026
Santiago, Chile
Energy Storage Summit Latin America brings together developers, investors, utilities and policymakers to explore how storage is advancing system stability, regulation, deployment and new revenue models across the region. With insights from Chile, Argentina, Brazil, Mexico and beyond, the Summit focuses on financing, policy clarity, hybridisation, supply chain development and project optimisation as LATAM accelerates its storage buildout.

Read Next

February 24, 2026
Fluctuating power prices in Europe present opportunities for BESS developers, according to speakers at the 2026 Energy Storage Summit.
February 24, 2026
Lightsource bp has sold a 1GW operational solar PV portfolio, with options to build 800MW of co-located battery storage, in Australia.
February 24, 2026
Wooderson Solar Development Co has secured federal environmental approval for a 450MW solar PV power plant with 3,600MWh of co-located battery energy storage in Queensland, Australia.
February 20, 2026
A flurry of BESS project news from big-name players in Western Europe in the run-up to the Energy Storage Summit next week, with Neoen, Statkraft, Zenobē and Infranode moving projects forward in Germany, Ireland, the UK and Denmark. Highlights include a 15-year toll between Drax and Zenobē, and multiple 4-hour duration systems.
Premium
February 19, 2026
We hear from Netherlands-based ‘distributed hybridisation’ sodium-ion BESS startup Moonwatt, as it announces its first project 18 months after being founded and around a year after executives introduced its tech and strategy to Energy-Storage.news.