Utility and independent power producer (IPP) Engie has started commercial operations of its 48MW/264MWh battery energy storage system (BESS) Capricornio project in the northern region of Antofagasta, Chile.

This is the company’s fourth operational BESS project in the country in the company after Arica (with a 2MW/2MWh capacity and operational since 2019), Coya (139MW/638MWh in March 2024) and Tamaya (68MW/418MWh) in October 2024. Engie invested US$73 million in the construction of its fourth operational BESS project in Chile which is co-located with the 87.9MW solar PV plant of the same name.

Similarly to the two projects brought online in 2024, a spokesperson for Engie told Energy-Storage.News that the batteries were provided by inverter and battery storage technology supplier Sungrow. In total, the project has 96 containers installed and batteries with a 5-hour duration.

The BESS market in Chile has been growing very quickly, so much so that in April, the country was one of the leading markets driving global BESS deployments (Premium access). That same month, Chile passed 1GW of operational BESS, according to Energy Minister Diego Pardow, after the operational launch of Atlas Renewable Energy’s standalone 200MW/800MWh BESS project in April this year.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“This type of solution enables a greater penetration of renewable energy generation projects and provides greater flexibility to the electrical system. Moreover, as Engie Group, we already have 5GW of storage capacity in operation and under construction globally,” said Juan Villavicencio, Managing Director Renewables and Batteries de ENGIE Chile.

Villavicencio added that the project is part of the company’s target to reach 3.5GW of operational capacity by 2027, of which more than 60% will come from renewables and energy storage.

Engie’s energy storage portfolio in Chile includes several other BESS projects currently under construction and targeted to be commissioned before the end of 2026. The projects are located in different regions of Chile, with one in the Metropolitan Region (Libélula) with a BESS capacity of 199MW/995MWh, one in the northern region of Atacama (BESS Los Loros) with a 46MW BESS output and two in the northern region of Antofagasta (Lile and BESS Tocopilla) with 140MW and 116MW BESS output respectively.

Returning for a fourth edition in Santiago, Chile, the Energy Storage Summit Latin America will explore opportunities in countries such as Chile, Peru, Colombia, Argentina, Brazil, the Dominican Republic and Puerto Rico. Join Solar Media on October 14-15 to meet with investors, policy makers, developers, utilities, network operators, technology providers, EPCs, consultants, law firms and more to make sure you are a part of the rapidly growing storage landscape in Latin America.

27 October 2026
Santiago, Chile
Energy Storage Summit Latin America brings together developers, investors, utilities and policymakers to explore how storage is advancing system stability, regulation, deployment and new revenue models across the region. With insights from Chile, Argentina, Brazil, Mexico and beyond, the Summit focuses on financing, policy clarity, hybridisation, supply chain development and project optimisation as LATAM accelerates its storage buildout.

Read Next

March 24, 2026
Envision Energy’s director of energy storage solutions, Michael Koller, speaks with Energy-Storage.news at Energy Storage Summit 2026 in London, UK.
Premium
March 23, 2026
Energy-Storage.news spoke exclusively with Argentina’s National Energy Secretary, María Tettamanti, about the launch of its second BESS tender.
March 17, 2026
A joint venture between TotalEnergies and Eren Groupe has submitted a 6GWh solar-plus-storage project for environmental approval in Australia’s Northern Territory (NT).
March 10, 2026
The Argentinian Government has launched a new battery energy storage system (BESS) tender seeking 700MW and 4-hour duration.
March 10, 2026
The NSW Independent Planning Commission has approved Edify Energy’s 400MWh Burroway solar-plus-storage project in Australia.