Elements Green receives GPS approval for 1.3GWh solar-plus-storage site in Queensland, Australia

May 19, 2025
LinkedIn
Twitter
Reddit
Facebook
Email
The solar-plus-storage site will be within the proposed Central Queensland renewable energy zone. Image: Elements Green.

UK-headquartered developer Elements Green has received grid connection approval from Powerlink Queensland and the Australian Energy Market Operator (AEMO) for a 1.3GWh solar-plus-storage site in Queensland, Australia.

The developer announced it has received its 5.3.4.A letter from the state-owned network operator and AEMO for its Eurimbula Hybrid Facility.

Elements Green claims this is Australia’s largest solar and battery energy storage project to have received Generator Performance Standard (GPS) approval. It will couple 696MWp of solar PV generation with a 666MW/1,332MWh battery energy storage system (BESS).

The hybrid facility will be located within the proposed Central Queensland renewable energy zone (REZ), approximately 50km southeast of Gladstone. Queensland is set to pursue the development of 12 REZ across the state to support the deployment of 22GW of renewables by 2035.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

However, with the recent election of the right-wing Liberal National Party (LNP) of Queensland, and several shifts in energy policy, leading to the cancellation of the 120GWh Pioneer-Burdekin pumped hydro project, question marks will be raised as to whether these will all be pursued.

For Elements Green, the receipt of the 5.3.4.A letter marks a vote of confidence in what will be the developer’s first solar-plus-storage project in Australia, with hopes to break ground on the site later this year.

Indeed, the letter grants the approval of performance standards and the System Strength Impact Assessment, as outlined in Clause 5.3.4A of AEMO’s National Electricity Rules.

Toby Roberts, country director of Elements Green Australia, said the project will benefit from “abundant sunshine, a stable grid, and strong regulatory support.”

According to documents submitted to Australia’s Environment Protection and Biodiversity Conservation (EPBC) Act, the hybrid facility will be spread across a 1,280-hectare area. The proposal includes the development of an onsite substation and will connect to the National Electricity Market (NEM) via existing 275kV transmission lines.

Development approval for the site was granted by the Gladstone Regional Council in 2018.

Elements Green is the second company to receive a 5.3.4.A letter for a solar-plus-storage site in recent weeks. Indeed, Energy-Storage.news reported on Friday (16 May) that developer Elgin Energy received grid connection approval for its 150MW Elaine solar-plus-storage project, situated in the Central Highlands region of Victoria.

Australia’s rigorous grid codes

Australia has one of the most rigorous grid code certification processes, which is part of AEMO’s GPS approval process, as noted by Energy-Storage.news in recent months.

Tom Best, the COO of Eku Energy, a company that develops, owns, and operates BESS, recently told ESN Premium that the procedure for developers in Australia to connect to the transmission grid and tap into the NEM Frequency Control Ancillary Services (FCAS) and energy trading markets is extremely stringent.

He also noted that it represents one of the longest and costly grid compliance processes among all the markets in which Eku Energy operates.

AEMO’s technicians subject plants to a wide variety of scenarios and ultimately push the plant or its model to the breaking point, which, as Best noted, necessitates project designers conducting numerous studies.

Once this is completed, the process is documented in a Grid Protection Scheme (GPS), which must then receive approval from both the Network Service Provider (NSP) and AEMO before the market operator issues the 5.3.4A letter of compliance.

However, the process does not end with the receipt of the 5.3.4A letter. Since the GPS is formulated based on modelling, any alterations made during the construction phase, such as modifications in plant design or cabling setups that might impact its electrical characteristics, must be updated through a procedure known as R1.

While a project can be awarded a GPS, the R1 process demonstrates that the project meets or surpasses its performance standards as required by AEMO and the network service providers. If these standards are not met, the GPS can be retracted.

17 March 2026
Sydney, Australia
As we move into 2026, Australia is seeing real movement in emerging as a global ‘green’ superpower, with energy storage at the heart of this. This Summit will explore in-depth the ‘exponential growth of a unique market’, providing a meeting place for investors and developers’ appetite to do business. The second edition will shine a greater spotlight on behind-the-meter developments, with the distribution network being responsible for a large capacity of total energy storage in Australia. Understanding connection issues, the urgency of transitioning to net zero, optimal financial structures, and the industry developments in 2026 and beyond.

Read Next

December 16, 2025
In this edition of the Energy-Storage.news US news roundup, EticaAG partners with Shell on battery immersion tech, Pacific Northwest National Laboratory begins utility-scale battery testing, and ON.Energy announces a transformer supply agreement.
December 16, 2025
 Utility Georgia Power has reached an agreement with the Public Interest Advocacy (PIA) staff of the Georgia Public Service Commission (PSC), that, if approved, will help lower energy costs and meet electricity demand in the state.
December 16, 2025
Global average prices for turnkey battery storage systems fell by almost a third year-over-year, with sharp cost declines expected to continue.
December 16, 2025
Waratah Super Battery developer Akaysha Energy has put the first phase of its Ulinda Park BESS project into operation in Queensland, Australia.
December 12, 2025
Utility Origin Energy has hired Wärtsilä to expand its battery storage installation at the Eraring coal power plant site in New South Wales, Australia.