Eco Stor puts largest BESS in Germany online, former majority owner building Finland project

June 6, 2025
LinkedIn
Twitter
Reddit
Facebook
Email

Owner-operator Eco Stor has connected what it claimed is the largest BESS in Germany to the grid, while its former majority owner is going to build a BESS in Finland.

The inauguration of the 103.5MW/238MWh battery energy storage system (BESS) project in Bollingstedt, Schleswig-Holstein, was announced yesterday (5 June) by the company on LinkedIn. It has been developed and deployed in partnership with developer EPW.

Eco Stor is a developer-operator that also has in-house engineering, procurement and construction (EPC) and system integration capabilities, with its Germany BESS projects designed with its own proprietary configuration. The firm originally also had its own BESS enclosure design, but now buys BESS from established providers.

Eco Stor launched construction on the Bollingstedt BESS a little over a year ago, and is also building an identically-sized project 5km away, called Schuby. It is also developing and building several much larger, 300MW/600MWh systems, part of its ‘Eco Power’ series.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Eco Stor was acquired by investors X-ELIO, part of global infra investor Brookfield, and Natural Infrastructure Capital (NIC) last year from majority owner Å Energi, a Norway-based utility, as covered by Energy-Storage.news.

While it wasn’t clear at the time of the deal, it now has been confirmed it was an outright acquisition but only of the Germany segment of Eco Stor – Eco Stor GmbH – with Eco Stor AS (Norway) remaining a separate, Å Energi-owned firm still active in BESS, as evidenced by a concurrent announcement.

Eco Stor AS building in Finland

The day before Eco Stor GmbH’s announcement, Eco Stor AS announced it had entered into an agreement to develop and install a 50MW/50MWh BESS near Isokangas in central Finland, with some construction already underway.

Eco Stor AS will build and co-own the BESS along with Norwegian investment company Farvatn and Finnish energy storage company AmpTank. The consortium has reached final investment decision (FID) on the project which is set to come online in 2026.

The Isokangas project is located close to wind generation areas in central Finland and is located by a substation belonging to Finnish transmission system operator (TSO) Fingrid. The project has built-in optionality to expand from a 1-hour to a 2-hour system.

“BESS market is expanding, supported by high expected growth of onshore wind and solar power. Our objective is to utilize the Isokangas project as a stepping stone towards building more BESS projects in Finland,” says Dr. Trygve Burchardt, CEO of Eco Stor AS.

The announcement explained the Germany sale: “In 2024, Eco Stor divested its German first life grid BESS subsidiary, including a multi-GW pipeline of utility-scale BESS projects, to Brookfield-owned renewable energy developer-operator X-ELIO and private equity firm Nature Infrastructure Capital.”

Other shareholders alongside Å Energi in Eco Stor AS include Klaveness Marine and Farvatn Capital, the announcement added.

Amptank, co-investor in the Isokangas project, recently sold a 30MW/60MWh project to investor UB Renewable Energy Fund (AIF).

Germany headwinds and opportunities discussed at Energy Storage Summit Germany

The announcements come during a week when Solar Media hosted the inaugural Energy Storage Summit Germany, co-located with the Battery Show Europe 2025, in Stuttgart (3-5 June).

Big talking points at the event were regulatory challenges including the BKZ and the threat of grid fees returning for BESS in 2029, as well as what the potential introduction of a Capacity Market (CM) would mean for BESS (Premium access).

9 June 2026
Stuttgart, Germany
Held alongside The Battery Show Europe, Energy Storage Summit provides a focused platform to understand the policies, revenue models and deployment conditions shaping Germany’s utility-scale storage boom. With contributions from TSOs, banks, developers and optimisers, the Summit explores regulation, merchant strategies, financing, grid tariffs and project delivery in a market forecast to integrate 24GW of storage by 2037.
15 September 2026
Berlin, Germany
Launching September 2026 in Berlin, Energy Storage Summit Germany is a new standalone event dedicated to Germany’s energy storage market. Bringing together investors, developers, policymakers, TSOs, manufacturers and optimisation specialists, the Summit explores the regulatory shifts, revenue models, financing strategies and technology innovations shaping large-scale deployment. With Germany targeting 80% renewables by 2030, it offers a focused platform to connect with the decision-makers driving the Energiewende and the future of utility-scale storage.
2 December 2026
Italy
Battery Asset Management Summit Europe is the annual meeting for owners, operators, investors, and optimisation specialists working with operational BESS assets across the continent. The Summit focuses on how to maximise performance and revenue, manage degradation, integrate advanced optimisation software, navigate evolving market and regulatory frameworks, and plan for repowering or end-of-life strategies. With insights from Europe’s most active storage markets, it equips attendees with practical guidance to run resilient, profitable battery portfolios as the sector scales.

Read Next

March 24, 2026
Arevon, Banpu Power (BPP) and Energy Vault have made BESS project announcements totalling 1,550MWh of capacity in the US.
March 24, 2026
Envision Energy’s director of energy storage solutions, Michael Koller, speaks with Energy-Storage.news at Energy Storage Summit 2026 in London, UK.
March 24, 2026
Utility and power firm Munch Energie is putting five large-scale BESS projects online in Germany. 
March 20, 2026
Indian solar PV module manufacturer Saatvik Green Energy is to enter the energy storage market through a newly launched subsidiary.
Premium
March 19, 2026
The price of BESS has fallen steadily in the past few years, but recent events look set to slow or event reverse that trend at least in the short term. Video interviewees at last month’s Energy Storage Summit 2026 shared their views on the topic.