CPUC approves California utility projects including PG&E’s 1.6GW/6.4GWh BESS

April 25, 2022
LinkedIn
Twitter
Reddit
Facebook
Email

The California Public Utilities Commission (CPUC) has approved new projects by the state’s three investor-owned utilities, including nine battery energy storage system (BESS) facilities proposed by PG&E totalling 1.6GW/6.4GWh.

The CPUC has approved the projects which were proposed by PG&E in January in response to an order to procure 11.5GW of clean energy capacity, under the CPUC’s internal resource planning process.

They will also partially contribute towards a portion of additional resources for Summer Reliability Targets for 2022 and 2023, a requirement enacted in December 2021 after extreme weather events that year placed a strain on the grid.

The resources have to come online between 2023 and 2026 but PG&E expects these nine (which total 1,598.7MW to be exact) will be fully operational by June 2024.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

They are all four-hour lithium-ion, stand-alone, transmission-connected BESS projects ranging from 80MW/320MWh to the the largest, Vistra’s 350MW/1,400MWh extension to Moss Landing, already the world’s largest BESS.

The nine BESS projects by PG&E

Project nameDeveloper/OwnerOutput/CapacityLocation Online date
Beaumont Energy StorageTerra-Gen100MW/400MWhBeaumont, Riverside CountyAugust 2023
Edwards Sanborn Energy StorageTerra-Gen169MW/676MWhMojave, Kern CountyAugust 2023
Canyon Country Energy StorageTerra-Gen80MW/320MWhSanta Clarita, LA CountyOctober 2023
MOSS350Vistra350MW/1400MWhMoss Landing, Monterey CountyAugust 2023
Inland Empire Energy StorageStrata Clean Energy100MW/400MWhRialto, San Bernadino CountyApril 2024
Corby Energy StorageNextEra Energy125MW/500MWhVacaville, Solano CountyJune 2024
Kola Energy StorageNextEra Energy275MW/1,100MWhTracy, Alameda CountyJune 2024
Nighthawk Storage Tenaska 300MW/1,200MWhPoway, San Diego County June 2024
Caballero Energy StorageOrigis99.7MW/398.8MWhNipomo, San Luis Obispo County June 2024

All nine will provide power to the California ISO (CAISO) grid under a Long-Term Resource Adequacy Agreement contract with a lifetime of 15 years. Resource Adequacy is CAISO’s programme to ensure the grid has enough capacity to deliver power to customers. The state aims to have a carbon-free grid by 2045.

PG&E procured the sites through a competitive tender process using net market value (NMV) and other qualitative factors like being located in a disadvantaged community.

BESS projects in The Golden State are now primarily making money through Resource Adequacy and wholesale energy trading, with an installed capacity of nearly 3GW and a frequency response market of only 500MW.

The CPUC has also approved the 2020 energy storage plans for all three investor-owned utilities, PG&E, SDG&E and SCE (Southern California Edison) which has seen them procure 1,325MW of power in response to Assembly Bill 2514, to come online by the end of 2024. SCE and PG&E have procured 580MW each while SDG&E has procured 165MW.

The CPUC has also authorised two clean energy programmes from SCE: a home energy storage pilot funded at US$5 million and a heat pump programme funded at US$13.9 million.

The commission also approved changes to SCE’s 20-year power purchase agreements (PPA) with two combined cycle gas power plants from AES. The agreement will provide an additional 49.5MW of power capacity and 16.5 MW of energy and ancillary services at no additional cost, the commission said.

24 March 2026
Dallas, Texas
The Energy Storage Summit USA is the only place where you are guaranteed to meet all the most important investors, developers, IPPs, RTOs and ISOs, policymakers, utilities, energy buyers, service providers, consultancies and technology providers in one room, to ensure that your deals get done as efficiently as possible. Book your ticket today to join us in 2026!
15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

February 26, 2026
Energy storage developer and subsidiary of Canadian Solar, Recurrent Energy, has sold its 200MWh Fort Duncan battery energy storage system (BESS) project, located in Texas, US, to developer Hunt Energy Network.
February 26, 2026
The US Department of Energy (DOE) has closed a US$26.5 billion loan package to two wholly owned subsidiaries of utility Southern Company, in Georgia and Alabama, US.
February 26, 2026
Large-scale renewable energy power plant developers in the Philippines have been instructed to integrate energy storage into their proposed facilities.
February 26, 2026
Utility Xcel Energy will install 30GWh of US startup Form Energy’s iron-air batteries at a data centre in Pine Island, Minnesota, belonging to tech giant Google.
February 25, 2026
Experts at the ongoing Energy Storage Summit 2026 have cautioned against treating co-located storage as a “silver bullet” to prop up commercially underperforming solar assets.