CellCube and G&W launch US microgrid solution with 2MW/8MWh project in Illinois

LinkedIn
Twitter
Reddit
Facebook
Email

Vanadium redox flow battery company CellCube and power electronics company G&W Electric have launched a microgrid solution for the US market, starting with a project at the latter’s HQ in Illinois, US.

CellCube (official name Enerox GmbH) and G&W Electric have signed a partnership agreement to offer a new and integrated microgrid solution to the US market. G&W Electric has added CellCube’s Vanadium Redox Flow Battery (VRFBs) as a key technology to its microgrid solution portfolio and has become a ‘Value Added Reseller’ for CellCube’s energy storage systems.

The partnership has been initiated through a microgrid project G&E Electric has built at its own headquarters in Bolingbrook, Illinois, with a bi-facial solar PV array of 6,000 panels coupled to a 2MW/8MWh system provided by CellCube.

G&W began work on the project in August 2021 which also includes a 1.3MVA flywheel. Energy-Storage.news previously reported that CellCube may have been the provider of the flow battery solution for the project and yesterday’s announcement confirmed it.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

CEO Alexander Schoenfeldt told Energy-Storage.news: “Commercial & industrial customers are recognising that longer durations support their need better to cover the numerous peaks over the day instead of using a one- or two-hour battery. In addition, they have an increased appetite to capitalise on the volatility in the market by capturing those peak prices and increase their own project IRR – longer duration storage is then a critical path.”

The microgrid will cover multiple use cases including ‘islanding’ capability, peak load shaving, sub cycle backup power for critical asset protection and will actively participate in utility Commonwealth Edison’s demand response program by isolating itself from the grid to help reduce peak load demand.

It will also participate in the ancillary service and energy trading markets run by grid operator PJM, which covers a handful of states in the eastern US. It will provide Frequency Regulation through PJM Interconnection, which helps ensure the grid remains stable at 60Hz.

The 2MW/8MWh VRFB is also capable of operating at up to 150% of its nominal power (so 3MW) for two hours to catch peak power prices in the PJM energy market.

G&W launched the project after its operations were completely shut down due to grid outages a few years ago.

“Power outages in some regions in the US are more likely than in central Europe, and big industrial companies want a solution for that. A resilient microgrid for multiple hours saves them a couple of hundred thousand in each case of an outage or even a flicker taking place,” Schoenfeldt said.

John Mueller, chairman and owner of G&W Electric said: “CellCube’s long duration battery technology unlocks huge value for G&W Electric with the lowest total lifecycle cost of any technology in the market. For us, it is an obvious step to partner with the market leader of Long-Duration Energy Storage.”

The Bolinbrook project and partnership with G&W is a good guide to CellCube’s short-term target market while utility-scale projects will come later, as Schoenfeldt explained:

“Taking into account the limitations in the supply chain we are looking into the microgrid market demand initially while preparing for large front-of-meter projects in the next years.”

Read Next

Premium
July 3, 2026
Energy-Storage.news Premium speaks with energy storage market experts Raafe Khan of Camelot Energy Group and Oliver Kerr of Aurora Energy Research on FERC’s recently issued show cause orders.
July 3, 2026
AGL has delivered a solar and battery microgrid described as “one of the largest privately owned non-mining microgrids in Australia”.
July 1, 2026
Independent power producer (IPP) Grenergy has signed a 1TWh night-time power purchase agreement (PPA) for its 3.5GWh Elena BESS project in Chile.
June 29, 2026
Two recent microgrid projects highlight the expanding role of flow batteries, with Quino Energy deploying organic flow batteries in the Maldives and the Paskenta Band of Nomlaki Indians integrating zinc hybrid cathode storage in Northern California.
June 26, 2026
IPP Enlight Renewable Energy has announced that its US subsidiary Clēnera Holdings has entered into a debt financing framework agreement for the CO Bar Complex in Arizona, US.