CellCube and G&W launch US microgrid solution with 2MW/8MWh project in Illinois

LinkedIn
Twitter
Reddit
Facebook
Email

Vanadium redox flow battery company CellCube and power electronics company G&W Electric have launched a microgrid solution for the US market, starting with a project at the latter’s HQ in Illinois, US.

CellCube (official name Enerox GmbH) and G&W Electric have signed a partnership agreement to offer a new and integrated microgrid solution to the US market. G&W Electric has added CellCube’s Vanadium Redox Flow Battery (VRFBs) as a key technology to its microgrid solution portfolio and has become a ‘Value Added Reseller’ for CellCube’s energy storage systems.

The partnership has been initiated through a microgrid project G&E Electric has built at its own headquarters in Bolingbrook, Illinois, with a bi-facial solar PV array of 6,000 panels coupled to a 2MW/8MWh system provided by CellCube.

G&W began work on the project in August 2021 which also includes a 1.3MVA flywheel. Energy-Storage.news previously reported that CellCube may have been the provider of the flow battery solution for the project and yesterday’s announcement confirmed it.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

CEO Alexander Schoenfeldt told Energy-Storage.news: “Commercial & industrial customers are recognising that longer durations support their need better to cover the numerous peaks over the day instead of using a one- or two-hour battery. In addition, they have an increased appetite to capitalise on the volatility in the market by capturing those peak prices and increase their own project IRR – longer duration storage is then a critical path.”

The microgrid will cover multiple use cases including ‘islanding’ capability, peak load shaving, sub cycle backup power for critical asset protection and will actively participate in utility Commonwealth Edison’s demand response program by isolating itself from the grid to help reduce peak load demand.

It will also participate in the ancillary service and energy trading markets run by grid operator PJM, which covers a handful of states in the eastern US. It will provide Frequency Regulation through PJM Interconnection, which helps ensure the grid remains stable at 60Hz.

The 2MW/8MWh VRFB is also capable of operating at up to 150% of its nominal power (so 3MW) for two hours to catch peak power prices in the PJM energy market.

G&W launched the project after its operations were completely shut down due to grid outages a few years ago.

“Power outages in some regions in the US are more likely than in central Europe, and big industrial companies want a solution for that. A resilient microgrid for multiple hours saves them a couple of hundred thousand in each case of an outage or even a flicker taking place,” Schoenfeldt said.

John Mueller, chairman and owner of G&W Electric said: “CellCube’s long duration battery technology unlocks huge value for G&W Electric with the lowest total lifecycle cost of any technology in the market. For us, it is an obvious step to partner with the market leader of Long-Duration Energy Storage.”

The Bolinbrook project and partnership with G&W is a good guide to CellCube’s short-term target market while utility-scale projects will come later, as Schoenfeldt explained:

“Taking into account the limitations in the supply chain we are looking into the microgrid market demand initially while preparing for large front-of-meter projects in the next years.”

3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.

Read Next

September 14, 2026
UAE state-owned renewables company Masdar has partnered with Germany’s Luxcara for battery storage and wind energy projects.
September 11, 2026
Greek renewables developer Metlen Energy & Metals has signed an agreement with utility Copec for the sale of the Tamarico II solar-plus-storage project in Chile’s Atacama region.
September 11, 2026
Our collection of user-posted analysis, views, and unofficial news, gathered from our networks on LinkedIn, returns for its third outing.
Premium
September 10, 2026
We hear from Angus Gordon Lennox, chair of the Gore Street Energy Storage Fund (GSF), which faces a shareholder vote next week on its future. 
September 10, 2026
The venture-capital-style returns once available in Australia have disappeared, according to panellists at the Battery Asset Management Summit Australia 2026.