Calpine to bring majority of 680MW California BESS online this summer

April 5, 2024
LinkedIn
Twitter
Reddit
Facebook
Email

Gas and geothermal plant operator Calpine Corporation will bring 510MW of its 680MW capacity battery energy storage system (BESS) project in California online in summer 2024, with BYD battery units.

The 510MW phase one of the Nova Power Bank will be complete this summer, with another 110MW coming online in autumn and the final 60MW in 2025, Calpine said this week.

It is the first time Calpine has officially announced the Nova project, with Energy-Storage.news reporting on it using various sources in January this year (Premium access), when White & Case announced a US$1 billion-plus financing round for it.

The 43-acre project is on the former site of Calpine’s Inland Empire legacy power plant, which it decommissioned in late 2022.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

It didn’t reveal the capacity of the project but said that it could power 680,000 homes for four hours, implying it has a 4-hour duration, as the vast majority of California projects do. That would make it 2,720MWh, slightly smaller than the two largest operational BESS projects in the world, Moss Landing (3,000MWh) and Edwards & Sanborn (3,272MWh), both also in California.

It said that utilities Southern California Edison (SCE), Peninsula Clean Energy, and San Diego Gas & Electric will use the electricity from the project, presumably through Resource Adequacy, grid operator CAISO’s means of ensuring there is enough power to supply demand with a reserve margin.

Based on previous documents from the California Public Utilities Commission (CPUC), SCE will specifically contract for the 110MW coming online in fall.

Calpine Corporation operates natural gas and geothermal resources across the US with 78 plants. It already has a 80MW BESS in operation in California, called Santa Ana, and two under construction in addition to Nova: the 25MW West Ford Flat BESS and the 13MW Bear Canyon BESS. The company claims to have 2,000MW of BESS in development in total.

15 September 2026
San Diego, USA
You can expect to meet and network with all the key industry players again in 2025 from major US asset owners, operators, RTOs and ISOs, optimizers, software and analytics providers, technical consultancies, O&M technology providers and more.

Read Next

May 1, 2026
Francesco Oppici, co-founder and CCO of Carbon dioxide-based long-duration energy storage (LDES) company Energy Dome tied the commercialisation path of LDES to data centres.
May 1, 2026
Large-scale BESS projects have been progressed to construction, financing or operations across the EU this week, by project owners, investors and EPC firms re:cap, LONGi, Teos, Flower, Goldbeck Solar, SPP and Tavion.
April 30, 2026
Carl Coe, chief of staff at the US Department of Energy stated that the Department cares about “affordable, reliable, available energy, regardless of source.”
Premium
April 29, 2026
Energy-Storage.news Premium speaks with Rob Greskowiak, chief commercial officer at Lightshift Energy, about the company’s distributed storage approach to the demand of PJM.
April 28, 2026
Utility DTE Energy has said it will forego customer rate increases for two years dependent on the success of a US$16 billion data centre campus involving a battery energy storage system (BESS).