California: SDG&E commissions 171MW of BESS, Ameresco enlisted for 379MWh of projects

LinkedIn
Twitter
Reddit
Facebook
Email

California utility San Diego Gas & Electric (SDG&E) has commissioned two projects totalling 171MW of battery storage, while system integrator Ameresco has secured contracts to deliver 379MWh at four gas plants in the state.

SDG&E announced the commissioning of the 131MW Westside Canal project and the 40MW Fallbrook project, located in Imperial Valley and San Diego county respectively. Westside came online last month while Fallbrook has been operational since May, having begun testing in late 2022.

Although the two projects’ energy storage capacity in MWh was not revealed, large-scale battery energy storage system (BESS) projects in the state tend to be four-hour systems, especially those delivered by or for California’s three investor-owned utilities: SDG&E, PG&E and SCE.

Four hours is the required duration to provide energy to utilities through long-term agreements through grid operator CAISO’s Resource Adequacy framework. Based on this, the two projects’ combined capacity could be 684MWh.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The projects are the third and fourth large-scale BESS units SDG&E has turned online in recent years, after it commissioned the 30MW Top Gun project in late 2021 and then the 30MW Kearny project late last year, both in San Diego. By the end of 2023, it expects to have 345MW of BESS online, sufficient to meet 15% of customer load on a typical day and 7% on a system peak day.

The projects are part of a fleet of large-BESS in the state which is helping it balance out peaks and troughs in demand, maintain grid flexibility, and move away from fossil fuel resources. California is seeing to become entirely carbon-neutral by 2045.

“With our state experiencing more frequent climate extremes such as record heat waves and droughts, it is essential to invest in innovations like energy storage to make sure we can continue to power the world’s 4th largest economy reliably,” said CAISO president and CEO Elliot Mainzer. “The rapid growth of energy storage in California in recent years gives me optimism about our state’s future and its capacity to respond to climate change.”

Ameresco to deliver 379Mh of BESS for Avenue Capital-owned group

In related news, system integrator Ameresco will deploy four BESS projects co-located with gas power plants owned by Middle River Power (MRP) across California. MRP is an independent power producer (IPP) owned by investment firm Avenue Capital.

The BESS projects will enhance the efficiency of MRP’s natural gas power plants, reducing their emissions and providing capacity to CAISO’s grid. MRP has eight gas plants in California, and ten nationwide.

Construction on the four projects will start this summer and is expected to be completed by Q3 of 2024.

“The energy storage assets allow for the shifting of solar energy from the middle of the day to supply the grid during evening peak hours, while maintaining our natural gas facilities as a flexible, reliable backstop,” said Mark Kubow, CEO of Middle River Power. “We are excited to introduce our first tranche of projects that takes such a meaningful step in helping California in the transition to more renewable resources.”

Legacy power plants make ideal locations for renewable energy and energy storage thanks to their large existing grid infrastructure. This has been particularly seen in the US market, and this week Energy-Storage.news reported on similar plans in Colombia.

Ameresco recently said it would get a three-site project totalling 2.1GWh of BESS capacity for one of the state’s three big IOUs, SCE, to “substantial completion by summer 2023”. The project made headlines last year with Ameresco invoking ‘force majeure’ clauses in its contract, citing the chaotic effect of Covid lockdowns in China on the BESS supply chain.

3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.
20 April 2027
Renaissance Dallas at Plano Legacy West Hotel, Dallas, Texas, Dallas
Policy, Procurement and Power Demand: Defining the Next Chapter for Energy Storage. Two days in Dallas where developers, IPPs, investors, utilities and the manufacturers building the technology come to close deals, not swap business cards. If you need to be in the room with the people deploying capital into US storage, this is that room.

Read Next

October 23, 2026
Tech giant Google and distributed energy resource (DER) platform Voltus have announced an expanded agreement to build a 1GW virtual power plant (VPP) in the US.
October 22, 2026
In recent North American sodium-ion news, Hithium is entering the Canadian market with two BESS solutions, while Peak Energy has closed a Series B financing round led by GM.
October 22, 2026
As demand for battery storage soars, the European Union (EU) has tried to grow its local battery supply chain with mixed success so far, writes PV ESS analyst Charlotte Gisbourne.
October 22, 2026
Science safety leader UL Solutions has announced a new certification pathway intended to help manufacturers of modular direct current (DC) battery energy storage systems (BESS).
October 21, 2026
Distributed energy storage company Viridi and developer and financier Good Carbon Co. have announced the deployment of a 3.75MWh energy storage project in Buffalo, New York.