Black & Veatch to evaluate proposals for 500MW pumped hydro plant in San Diego

LinkedIn
Twitter
Reddit
Facebook
Email
Bad Creek, an existing pumped hydro plant in South Carolina. Image: Duke Energy.

Infrastructure EPC company Black & Veatch will evaluate proposals received for a 500MW pumped hydro energy storage facility in San Diego, California.

San Diego Water Authority issued a request for proposals (RfP) for the plant last summer, with a 12 September 2017 deadline for submissions. The RfP was for a facility with 5-8 hours energy storage duration, to help support the stability of the local grid at peak times and to integrate local renewable energy production, mostly solar PV. Selling energy or services from the plant could also raise revenues for the Water Authority by reducing “upward pressure on water rates” caused by the need to deal with the ageing of the authority’s water infrastructure.

In short, through creating a new, smaller reservoir above the existing San Vicente Reservoir as well as tunnelling and power equipment including reversible pump turbines to link the two, water will flow downhill and drive the turbines during peak hours. At off-peak times, solar and other surplus power generation will be used to pump the water back to the upper reservoir.

A feasibility study by the authority found the project is likely to feature four 125MW turbines, while existing high voltage transmission infrastructure could support it. Dubbed the San Vicente Energy Storage Facility (SVESF) at San Vicente Reservoir, Black & Veatch has been selected as “owner’s representative” to the project by the Water Authority.

This article requires Premium SubscriptionBasic (FREE) Subscription

Enjoy 12 months of exclusive analysis

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Annual digital subscription to the PV Tech Power journal
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

“This project would marry investments in water system resilience with renewable energy deployment, helping to reduce greenhouse gases,” Black & Veatch associate vice president and project manager Kevin Davis said.

Black & Veatch recently delivered water storage facilities to San Diego Water Authority that enables six month reserve supplies and has already worked at San Vicente Reservoir, doubling its capacity. The company has also designed a 4.5MW pressure control and hydroelectric facility for the authority, which helps integrate local surplus renewable energy production.

Read Next

Premium
August 28, 2025
Energy-Storage.news Premium speaks with Sergio Melendez, storage sector manager at CAISO, and Ali Karimian, market optimisation director at GridBeyond, about regulating Bid Cost Recovery Payments in the California Independent System Operator market.
August 28, 2025
California utility Pacific Gas and Electric (PG&E) has pushed back recommissioning of the Elkhorn battery energy storage system (BESS) by approximately one year, to 30 June 2026.
August 28, 2025
European Commission funding is supporting a project to integrate battery storage at a pumped hydro energy storage (PHES) plant in Slovakia.
Premium
August 27, 2025
Following in the footsteps of several other US jurisdictions this year, officials at California’s Orange County are one step closer to amending zoning laws to allow the development of BESS. 
August 26, 2025
After an initial rush to deploy that gave CAISO and ERCOT the lead in US BESS adoption, both markets are focused on capacity and availability, writes Amit Mathrani of Rabobank Americas.

Most Popular

Email Newsletter