BELECTRIC installs storage system for Audi using second-life batteries

By John Parnell
May 29, 2019
LinkedIn
Twitter
Reddit
Facebook
Email
The 1.9MWh energy storage system is unveiled in Berlin. Source: BELECTRIC

BELECTRIC has completed a 1.9MWh energy storage system using second life electric vehicle (EV) batteries, for Audi in Berlin.

The project has been built at the EUREF Campus, a high-tech, low carbon innovation cluster. The system uses 20 batteries from test vehicles owned by Audi.

“On the EUREF Campus, we’ve seen a present-day example of how the energy and transport sectors can work together effectively and [harmonious] in the future. I’m pleased that BELECTRIC has been able to be part of this groundbreaking project,” said Frank Amend, the BELECTRIC Management Board member responsible for batteries and hybrid systems.

The Audi install will perform a number of tasks including grid stability, arbitrage, peak shaving, reactive power and partnering with a co-generation plant. A number of buildings on the campus have solar installed.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

“This battery storage system will allow Audi to provide an important link between volatile generation from renewable energy sources, different consumers and state-of-the-art power grids,” said Amend. “At BELECTRIC, we assisted with system integration for this storage facility by drawing on the wide experience we’ve been able to gain from our extensive track record of implementing other storage projects.”

The installation is part of the Mobility2Grid project, which has brought together a consortium of companies including Audi, BMW, Cisco and Siemens.

24 February 2026
InterContinental London - The O2, London, UK
This isn’t just another summit – it’s our biggest and most exhilarating Summit yet! Picture this: immersive workshop spaces where ideas come to life, dedicated industry working groups igniting innovation, live podcasts sparking lively discussions, hard-hitting keynotes that will leave you inspired, and an abundance of networking opportunities that will take your connections to new heights!

Read Next

Premium
December 1, 2025
We caught up with developer and IPP Greenvolt Power’s head of storage Antonio Montoto Rojo about the recent MACSE auction in Italy, where it won a contract for a 75MW BESS.
December 1, 2025
Estonia-headquartered high-power energy storage startup Skeleton Technologies officially opened two European production plants in November.
December 1, 2025
European BESS news from project owners Premier Energy Group, Verbund, Eco Stor, Ingrid Capacity, Ric Energy, Ganfeng Lithium, EP Group, RWE and Giga Storage, securing acquisitions, financings and route-to-market (RTM) deals for multiple gigawatts of capacity this past week.
November 25, 2025
There is a “healthy pipeline of projects in development” across Europe’s energy storage sector, but the technologies are as yet “significantly underutilised” below their potential.
November 25, 2025
A week of claimed first-of-their-kind advances in Germany’s BESS market, including the combination of monitoring, diagnostics and energy trading on one platform, an optimisation deal allowing multiple companies to trade one asset, and a law change accelerating permitting.