UK-based renewables developer Anesco says the inclusion of battery storage has been central to the economic viability of the country’s first subsidy-free solar farm, a 10MW site the company has just unveiled in the east of England.

Clayhill Solar Farm, near Flitwick in Bedfordshire, was developed by Anesco in just 12 weeks with work being conducted over the course of this summer and, crucially, after the Renewables Obligation scheme had closed to new applicants.

“For the solar industry, Clayhill is a landmark development and paves the way for a sustainable future, where subsidies are no longer needed or relied upon. Importantly, it proves that the Government’s decision to withdraw subsidies doesn’t have to signal the end of solar as a commercially viable technology,” Steve Shine, chief executive at Anesco, said.

The site – which has been shortlisted for this year’s Solar Power Portal Awards in the Ground-mount Solar PV Project category – is co-located with a 6MW battery storage facility which the company said was crucial to being able to make the development economically feasible without subsidy support.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Shine also paid testament to the firm’s supply chain in assisting with what he dubbed a “landmark” achievement for UK solar.

“Given our extensive experience with solar and storage projects, we took a fresh look at how we could finance and develop Clayhill without needing a renewables subsidy. We sought the views of our supply chain and with them looked at every aspect of the project – its design, the technical specifications, the use of the very latest technology and the costs of the various components,” he said.

Chinese manufacturer BYD supplied both the solar panels and the battery storage units while Huawei supplied the inverters.

The Huawei-built inverters are also considered to be a crucial factor in the site’s subsidy-free nature. Anesco said it was the first time the manufacturer’s “ground-breaking” 1,500V inverters have been deployed in Europe and are used to maximise power conversion.

UK politician, climate change minister Claire Perry, is to formally open the site at a ceremony later today and she described the development as a “significant moment for clean energy in the UK”.

“Solar panels already provide enough electricity to power 2.7 million homes with 99% of that capacity installed since 2010. The Government is determined to build on this success and our ambitious Clean Growth Strategy will ensure we continue to lead the world on the transition to a low carbon economy,” she added.

Anesco recently made headlines when the UK’s national energy regulator Ofgem ruled earlier this month that three of the developer’s 5MW solar farms could retain their financial support under the government’s Renewable Obligations (RO) scheme after retrofitting energy storage batteries. Anesco made a big move into solar-plus-storage in April when it retrofitted 12MWh of energy storage to 10 of its large-scale PV plants around Britain.

3 November 2026
Málaga, Spain
Understanding technology and supplier selection for Europe’s utility-scale PV market in 2027. PV ModuleTech Europe 2026 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of PV module, inverter and battery supplier selection; product availability, technology offerings, supply chain traceability, quality assurance, factory auditing, system reliability, and supplier bankability.

Read Next

October 29, 2026
The California Energy Commission (CEC) has released over US$46 million for the state’s Distributed Electricity Backup Assets (DEBA) Programme.
October 27, 2026
India has 5.3GWh of operational battery energy storage system (BESS) capacity, with a further 185GWh of projects under development, according to Prashant Bhamu, deputy director of integrated resources planning at the Central Electricity Authority (CEA), part of the Ministry of Power.
October 27, 2026
IPP Greenvolt has agreed to sell two BESS in Poland to A&R, PGE Group has started building an 800MWh one, while SC Holding, Tauron and Tavion have launched projects into the country.
October 23, 2026
Tech giant Google and distributed energy resource (DER) platform Voltus have announced an expanded agreement to build a 1GW virtual power plant (VPP) in the US.
October 23, 2026
German home energy storage and virtual power plant (VPP) company sonnen GmbH, sold by gas major Shell in August, has filed for insolvency.