‘Batteries cost-effective alternative to fossil fuels’, UK grid operator flexibility project finds

July 7, 2020
LinkedIn
Twitter
Reddit
Facebook
Email
Inside the 41MW Bloxwich battery energy storage system in England. Image: Arenko.

Batteries can offer a cost-effective option for upward and downward reserve to the UK grid, a project run by AI and automation tech firm Arenko with transmission network operator National Grid ESO has found.

The trial, first announced in May, found that the Electricity National Control Centre (ENCC) can effectively request the availability of sustained upward and downward reserve using a new operational agreement. As such, batteries offer a real alternative to thermal power plants and Combined Cycle Gas Turbines in particular.

Arenko’s flexible software architecture and automation technology was used to control the 41MW Bloxwich battery in the Midlands of England – which was recently acquired by publicly listed investment fund Gresham House Energy Storage Fund – to provide flexibility and highlight how batteries can be used to balance the system outside of just the frequency response market. Arenko partnered with US electrical industry giant GE on the Bloxwich project, Energy-Storage.news reported in 2018, as GE looked to use that project as a first step into the UK market.

The ENCC determined whether to request upward or downward reserve, following which Arenko provided bid and offer prices. The centre then provided an economic assessment of meeting reserve requirements using Arenko’s bid in comparison to other options.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

Two windows were then selected for the trial, during which the operational agreement was activated and the ENCC could call on Arenko’s battery for upward and downward reserve.

The battery was instructed in 11 settlement periods, providing 53.3MWh of negative reserve and 29.9MWh of positive reserve, providing a net cash flow of £96 (US$120.31). The activation of operational arrangement for upward and downward reserve results in the total payment (rounded to nearest pound) of £3342.

National Grid ESO and Arenko will now run further trials through July and September 2020 with a broader number of batteries.

To read the full version of this story visit Current±.

Read Next

Premium
December 10, 2025
Last month was the first time since June that both pre-application submissions and full planning consent submissions for grid-scale UK BESS surpassed 1GWh – just before NESO announced the results of its grid connection queue reshuffle.
December 10, 2025
AFC and public-private-partnership (PPP) Cabeolica have inaugurated 13.5MW of wind power generation and 26MWh of battery storage in Cape Verde.
December 9, 2025
The UK’s National Energy System Operator (NESO) will offer grid connection offers up to 2035 to 283GW of projects following a reform of the process.
December 2, 2025
Manoa Energy and HD Renewable Energy Japan have begun commercial operation of a 50MW/104MWh battery storage project in Hokkaido, Japan.
December 1, 2025
European BESS news from project owners Premier Energy Group, Verbund, Eco Stor, Ingrid Capacity, Ric Energy, Ganfeng Lithium, EP Group, RWE and Giga Storage, securing acquisitions, financings and route-to-market (RTM) deals for multiple gigawatts of capacity this past week.