Australia’s Waratah Super Battery enters planned shutdown amid transformer replacement efforts

November 24, 2025
LinkedIn
Twitter
Reddit
Facebook
Email

Developer Akaysha Energy has confirmed that the 850MW Waratah Super Battery in Australia will undergo a planned balance of plant shutdown from 20 November to 2 December 2025.

It comes as the BlackRock-backed developer continues to address the aftermath of a catastrophic transformer failure that occurred in October.

The 850MW/1,680MWh battery energy storage system, currently operating at a reduced 350MW capacity, maintains its System Integrity Protection Scheme (SIPS) service requirements, despite transformer issues that have delayed the full commissioning of what was designed to be the world’s most powerful battery storage system.

Estimates suggest the transformer failure could result in total losses between AU$50-80 million (US$32-51 million), according to Dr Tom Harries, partner at NARDAC, a specialist energy and infrastructure broker that provides battery energy storage insurance.

This article requires Premium SubscriptionBasic (FREE) Subscription

Try Premium for just $1

  • Full premium access for the first month at only $1
  • Converts to an annual rate after 30 days unless cancelled
  • Cancel anytime during the trial period

Premium Benefits

  • Expert industry analysis and interviews
  • Digital access to PV Tech Power journal
  • Exclusive event discounts

Or get the full Premium subscription right away

Or continue reading this article for free

The final loss amount depends on the timing of transformer replacement and whether a delay in start-up coverage applies to the project.

“If the project can replace the transformers in six months, possibly under a delay in start-up cover depending on whether the project has fully gone live or is still in testing, then the loss could be as low as AU$50 million,” Harries told Energy-Storage.news.

“However, this is contingent on securing transformers fairly quickly; otherwise, a much larger claim is likely.”

Main power transformer replacement typically requires extended lead times, with specialised equipment often taking 12-18 months to manufacture and deliver.

However, the transformers were manufactured by an Australian-based company (Wilson Transformer), providing advantages for the diagnostic and rectification process. In doing so, all diagnostic, rectification and re-commissioning activities can be undertaken locally, allowing faster turnaround times and close oversight of the repair process.

The transformer failure represents a significant setback for the BlackRock-owned project, which serves as Australia’s “giant shock absorber for the power grid”.

Located at the former Munmorah coal-fired power station site near Budgewoi, the facility monitors 36 transmission lines in real time and responds within seconds to grid disturbances.

Akaysha Energy CEO Nick Carter described the transformer incident as a “catastrophic failure” in an internal memo, highlighting the severity of the technical issue that has reduced the project’s operational capacity by more than half.

The scheduled shutdown is part of routine maintenance and has been coordinated with AEMO and Transgrid for several months.

It will affect the project’s current 350MW operational capacity during a critical period for Australia’s electricity system. The timing coincides with increasing summer demand patterns and ongoing challenges in managing renewable energy intermittency across the National Electricity Market (NEM).

Akaysha Energy expects the battery storage system’s remaining capacity to return online during 2026, according to a spokesperson.

24 February 2026
InterContinental London - The O2, London, UK
This isn’t just another summit – it’s our biggest and most exhilarating Summit yet! Picture this: immersive workshop spaces where ideas come to life, dedicated industry working groups igniting innovation, live podcasts sparking lively discussions, hard-hitting keynotes that will leave you inspired, and an abundance of networking opportunities that will take your connections to new heights!

Read Next

November 21, 2025
The development of data centres has emerged as a possible lifeline for ongoing projects in the battery energy storage system (BESS) industry.
November 21, 2025
In a major week for European BESS deal-making, project acquisition and financing deals have been done in the Poland, Germany, Finland, the UK and Romania for grid-scale projects totalling well over 1GW of capacity.
November 20, 2025
From the US, Maxwell Technologies is acquired for its third time, by Clarios, Fullmark Energy completes a tax credit transfer, and OATI partners with Colville Tribes on microgrid solutions.
November 20, 2025
Pacific Green’s Portland Energy Park, Victoria’s largest BESS at 1GW/2.5GWh, has secured federal approval via Australia’s EPBC Act.
November 20, 2025
Battery energy storage systems in Australia’s NEM are facing new operational and revenue challenges due to minimum system load events.